Washington

Named in 2 projects in the 2025 GA ITS Ten-Year Plan (2026-2035), plus 1 on its cancelled or completed lists.

—county (not printed)
—kV in the quote
MEAGproject sponsor
2projects in the plan

The plan prints no county for this substation, and no utility project page found names one for it.

Projects naming this substation

As the plan prints them. The sponsor is the project’s; one project can split work between owners.

ProjectSponsorWhere in the planNeed dateChange from the previous planSubstations named
MEAG: RAY PLACE RD - WASHINGTON 115kV LINE REBUILD
Rebuild approximately 17.4 miles of the Ray Place Rd - Washington 115kV line using 100C 795 ACSR conductor and upgrade limiting elements at substation along the line.
TEAMS 20270 · plan p.141 · zone 215
MEAG In the plan
p.11
Jun 1, 2027 Delayed from 2026 to 2027. Ray Place Rd, Washington
MEAG: RAY PLACE RD - WASHINGTON (WASHNGTN - WASHNGTN 3) 115kV
Rebuild approximately 1.6 miles of the Ray Place Rd - Washington 115kV line using 100C 1351 ACSR conductor. Upgrade limiting element at substation along the line.
TEAMS 20271 · plan p.142 · zone 215
MEAG In the plan
p.11
Jun 1, 2027 Delayed from 2026 to 2027 Ray Place Rd, Washington

On the cancelled or completed lists

ProjectSponsorWhere in the planNeed dateChange from the previous planSubstations named
GTC: ANTHONY SHOALS - WASHINGTON 115 kV LINE REBUILD
TEAMS 20010 · zone 215
Not printed Completed list
p.26
Dec 31, 2025
as listed
— Anthony Shoals, Washington

Source: 2025 GA ITS Ten-Year Plan (2026-2035), filed by Georgia Power Company as its Annual Transmission Update in Georgia PSC Docket 56002 on February 27, 2026; public disclosure version, retrieved 2026-11-20.