Ray Place Rd
Named in 3 projects in the 2025 GA ITS Ten-Year Plan (2026-2035).
—county (not printed)
—kV in the quote
MEAGproject sponsor
3projects in the plan
The plan prints no county for this substation, and no utility project page found names one for it.
Projects naming this substation
As the plan prints them. The sponsor is the project’s; one project can split work between owners.
| Project | Sponsor | Where in the plan | Need date | Change from the previous plan | Substations named |
|---|---|---|---|---|---|
| MEAG: RAY PLACE RD - WARRENTON PRIMARY 115kV RECONDUCTOR Reconductor approximately 10 miles of the Ray Place - Warrenton Primary 115kV line with 170C ACSS conductor. Upgrade limiting element at substation along the line. TEAMS 20264 · plan p.143 · zone 215 |
MEAG | In the plan p.11 |
Jun 1, 2027 | No change | Ray Place, Ray Place Rd, Warrenton Primary |
| MEAG: RAY PLACE RD - WASHINGTON 115kV LINE REBUILD Rebuild approximately 17.4 miles of the Ray Place Rd - Washington 115kV line using 100C 795 ACSR conductor and upgrade limiting elements at substation along the line. TEAMS 20270 · plan p.141 · zone 215 |
MEAG | In the plan p.11 |
Jun 1, 2027 | Delayed from 2026 to 2027. | Ray Place Rd, Washington |
| MEAG: RAY PLACE RD - WASHINGTON (WASHNGTN - WASHNGTN 3) 115kV Rebuild approximately 1.6 miles of the Ray Place Rd - Washington 115kV line using 100C 1351 ACSR conductor. Upgrade limiting element at substation along the line. TEAMS 20271 · plan p.142 · zone 215 |
MEAG | In the plan p.11 |
Jun 1, 2027 | Delayed from 2026 to 2027 | Ray Place Rd, Washington |
Source: 2025 GA ITS Ten-Year Plan (2026-2035), filed by Georgia Power Company as its Annual Transmission Update in Georgia PSC Docket 56002 on February 27, 2026; public disclosure version, retrieved 2026-11-20.
Before relying on any of this
- The plan prints no county for a substation. A county shown here is printed in the plan beside the station, or on a Georgia Power or Georgia Transmission project page that names the same station and one county.
- Project Sponsor belongs to the project, not to each station; one project can split work between owners.
- Costs are redacted in the public version of the plan and are not shown.