Named in 2 projects in the 2025 GA ITS Ten-Year Plan (2026-2035).

—county (not printed)
—kV in the quote
SAVproject sponsor
2projects in the plan

The plan prints no county for this substation, and no utility project page found names one for it.

Projects naming this substation

As the plan prints them. The sponsor is the project’s; one project can split work between owners.

ProjectSponsorWhere in the planNeed dateChange from the previous planSubstations named
SAV: CC - BIG OGEECHEE 500/230kV (NETWORK IMPROVEMENTS)
Construct a new substation near Little Ogeechee, adjacent to the 500kV and 230kV McCall Road - Thalmann 500kV and the Little Ogeechee - Meldrim 230kV Black and White lines. The new substation will loop in the existing McCall Road - Thalmann 500kV line, the existing Little Ogeechee - Meldrim 230kV lines, and accommodate a new 500/230kV auto transformer with an additional 230kV connection to Little Ogeechee.
TEAMS 19966 · plan p.105 · zone 219
SAV In the plan
p.8
Jun 1, 2026 No change Big Ogeechee, Little Ogeechee, McCall Road, Meldrim, Thalmann
SAV: COLEMAN - MELDRIM 115kV LINE RECONDUCTOR
Rebuild the Coleman - Meldrim 115kV line from Four Lakes - Structure 76A, approximately 8.1 miles, using 200C 1351 ACSS Martin. Upgrade two switches at Quacco Rd to a higher rating.
TEAMS 20784 · plan p.220 · zone 219
SAV In the plan
p.17
Jun 1, 2029 Advanced from 2032 to 2029 Coleman, Meldrim

Source: 2025 GA ITS Ten-Year Plan (2026-2035), filed by Georgia Power Company as its Annual Transmission Update in Georgia PSC Docket 56002 on February 27, 2026; public disclosure version, retrieved 2026-11-20.

Before relying on any of this

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first