LaGrange
Named in 3 projects in the 2025 GA ITS Ten-Year Plan (2026-2035).
—county (not printed)
—kV in the quote
GPC, GTCproject sponsor
3projects in the plan
The plan prints no county for this substation, and no utility project page found names one for it.
Projects naming this substation
As the plan prints them. The sponsor is the project’s; one project can split work between owners.
| Project | Sponsor | Where in the plan | Need date | Change from the previous plan | Substations named |
|---|---|---|---|---|---|
| GTC: LAGRANGE - NORTH OPELIKA 230 kV NEW LINE Build a new 230kV line from Lagrange to North Opelika (APC), 29.4 miles, with 200C ACSS 1351.5 Martin Conductor. TEAMS 19334 · plan p.111 · zone 213 |
GTC | In the plan p.9 |
Dec 1, 2026 | Delayed within 2026 | LaGrange, NORTH OPELIKA |
| GTC: DRESDEN JUMPER REPLACEMENT Upgrade the limiting jumpers at Dresden on the Dresden - LaGrange 230kV line with higher rated jumpers. TEAMS 19598 · plan p.98 · zone 213 |
GTC | In the plan p.8 |
Jun 1, 2026 | No change | Dresden, LaGrange |
| CORN CRIB - LAGRANGE 115kV RECONDUCTOR Reconductor a 14.1 miles section of the Corn Crib - LaGrange 115kV line with C7 Tortuga conductor. Replace limiting elements at Corn Crib. TEAMS 21324 · plan p.159 · zone 213 |
GPC | In the plan p.13 |
Jun 1, 2028 | New project | Corn Crib, LaGrange |
Source: 2025 GA ITS Ten-Year Plan (2026-2035), filed by Georgia Power Company as its Annual Transmission Update in Georgia PSC Docket 56002 on February 27, 2026; public disclosure version, retrieved 2026-11-20.
Before relying on any of this
- The plan prints no county for a substation. A county shown here is printed in the plan beside the station, or on a Georgia Power or Georgia Transmission project page that names the same station and one county.
- Project Sponsor belongs to the project, not to each station; one project can split work between owners.
- Costs are redacted in the public version of the plan and are not shown.