Kraft

Named in 2 projects in the 2025 GA ITS Ten-Year Plan (2026-2035).

—county (not printed)
—kV in the quote
SAVproject sponsor
2projects in the plan

The plan prints no county for this substation, and no utility project page found names one for it.

Projects naming this substation

As the plan prints them. The sponsor is the project’s; one project can split work between owners.

ProjectSponsorWhere in the planNeed dateChange from the previous planSubstations named
SAV: GOSHEN (SAV) - KRAFT 115kV LINE RECONDUCTOR
Rebuild a 3.48 miles section of the Goshen - Kraft 115kV line from 100C 795 ACSR Drake to 200C 1351 ACSS Martin.
TEAMS 20785 · plan p.146 · zone 219
SAV In the plan
p.12
Jun 1, 2027 No change Goshen, Kraft
SAV: GOSHEN (SAV) - KRAFT 115kV LINE REBUILD
Rebuild 3.04 miles of the Goshen - Kraft 115kV line from 100C 795 ACSR Drake to 200C 1351 ACSS Martin.
TEAMS 21297 · plan p.283 · zone 219
SAV In the plan
p.21
Jun 1, 2031 New project Goshen, Kraft

Source: 2025 GA ITS Ten-Year Plan (2026-2035), filed by Georgia Power Company as its Annual Transmission Update in Georgia PSC Docket 56002 on February 27, 2026; public disclosure version, retrieved 2026-11-20.