Goshen
Named in 3 projects in the 2025 GA ITS Ten-Year Plan (2026-2035).
—county (not printed)
—kV in the quote
MEAG, SAVproject sponsor
3projects in the plan
The plan prints no county for this substation, and no utility project page found names one for it.
Projects naming this substation
As the plan prints them. The sponsor is the project’s; one project can split work between owners.
| Project | Sponsor | Where in the plan | Need date | Change from the previous plan | Substations named |
|---|---|---|---|---|---|
| SAV: GOSHEN (SAV) - KRAFT 115kV LINE RECONDUCTOR Rebuild a 3.48 miles section of the Goshen - Kraft 115kV line from 100C 795 ACSR Drake to 200C 1351 ACSS Martin. TEAMS 20785 · plan p.146 · zone 219 |
SAV | In the plan p.12 |
Jun 1, 2027 | No change | Goshen, Kraft |
| MEAG: GOSHEN AREA STRATEGIC SOLUTION GPC: Construct a 230kV switching station on the Waynesboro - Wilson 230kV line. MEAG: Build a new 230kV line between the switching station and Goshen, approximately 12.3 miles using 200C 1351 ACSS conductor. GTC: Reconfigure Goshen substation and provide accommodations for the new 230kV line. TEAMS 21116 · plan p.262 · zone 215 |
MEAG | In the plan p.19 |
Jun 1, 2030 | No change | Goshen, Waynesboro, Wilson |
| SAV: GOSHEN (SAV) - KRAFT 115kV LINE REBUILD Rebuild 3.04 miles of the Goshen - Kraft 115kV line from 100C 795 ACSR Drake to 200C 1351 ACSS Martin. TEAMS 21297 · plan p.283 · zone 219 |
SAV | In the plan p.21 |
Jun 1, 2031 | New project | Goshen, Kraft |
Source: 2025 GA ITS Ten-Year Plan (2026-2035), filed by Georgia Power Company as its Annual Transmission Update in Georgia PSC Docket 56002 on February 27, 2026; public disclosure version, retrieved 2026-11-20.
Before relying on any of this
- The plan prints no county for a substation. A county shown here is printed in the plan beside the station, or on a Georgia Power or Georgia Transmission project page that names the same station and one county.
- Project Sponsor belongs to the project, not to each station; one project can split work between owners.
- Costs are redacted in the public version of the plan and are not shown.