Named in 3 projects in the 2025 GA ITS Ten-Year Plan (2026-2035).

—county (not printed)
—kV in the quote
MEAG, SAVproject sponsor
3projects in the plan

The plan prints no county for this substation, and no utility project page found names one for it.

Projects naming this substation

As the plan prints them. The sponsor is the project’s; one project can split work between owners.

ProjectSponsorWhere in the planNeed dateChange from the previous planSubstations named
SAV: GOSHEN (SAV) - KRAFT 115kV LINE RECONDUCTOR
Rebuild a 3.48 miles section of the Goshen - Kraft 115kV line from 100C 795 ACSR Drake to 200C 1351 ACSS Martin.
TEAMS 20785 · plan p.146 · zone 219
SAV In the plan
p.12
Jun 1, 2027 No change Goshen, Kraft
MEAG: GOSHEN AREA STRATEGIC SOLUTION
GPC: Construct a 230kV switching station on the Waynesboro - Wilson 230kV line. MEAG: Build a new 230kV line between the switching station and Goshen, approximately 12.3 miles using 200C 1351 ACSS conductor. GTC: Reconfigure Goshen substation and provide accommodations for the new 230kV line.
TEAMS 21116 · plan p.262 · zone 215
MEAG In the plan
p.19
Jun 1, 2030 No change Goshen, Waynesboro, Wilson
SAV: GOSHEN (SAV) - KRAFT 115kV LINE REBUILD
Rebuild 3.04 miles of the Goshen - Kraft 115kV line from 100C 795 ACSR Drake to 200C 1351 ACSS Martin.
TEAMS 21297 · plan p.283 · zone 219
SAV In the plan
p.21
Jun 1, 2031 New project Goshen, Kraft

Source: 2025 GA ITS Ten-Year Plan (2026-2035), filed by Georgia Power Company as its Annual Transmission Update in Georgia PSC Docket 56002 on February 27, 2026; public disclosure version, retrieved 2026-11-20.