Hartwell Energy

Named in 2 projects in the 2025 GA ITS Ten-Year Plan (2026-2035).

—county (not printed)
—kV in the quote
GPC, GTCproject sponsor
2projects in the plan

The plan prints no county for this substation, and no utility project page found names one for it.

Projects naming this substation

As the plan prints them. The sponsor is the project’s; one project can split work between owners.

ProjectSponsorWhere in the planNeed dateChange from the previous planSubstations named
HARTWELL DAM - HARTWELL ENERGY 230kV SERIES REACTORS
Replace the series reactors on the Hartwell Dam - Hartwell Energy 230kV line with larger size.
TEAMS 21111 · plan p.80 · zone 212
GPC In the plan
p.19
Jun 1, 2030 No change Hartwell Dam, Hartwell Energy
GTC: CASH CREEK - HARTWELL ENERGY 230kV LINE
Construct a new 230kV line, approx. 35 miles, from Hartwell Energy to Middle Fork, using (2) 200C 1351 ACSS conductor. Expand Hartwell Energy 230kV and Middle Fork 230kV substations for the new line termination.
TEAMS 21113 · plan p.79 · zone 212
GTC In the plan
p.19
Jun 1, 2030 No change Cash Creek, Hartwell Energy, Middle Fork

Source: 2025 GA ITS Ten-Year Plan (2026-2035), filed by Georgia Power Company as its Annual Transmission Update in Georgia PSC Docket 56002 on February 27, 2026; public disclosure version, retrieved 2026-11-20.