Gordon

Named in 3 projects in the 2025 GA ITS Ten-Year Plan (2026-2035).

—county (not printed)
—kV in the quote
GPC, GTCproject sponsor
3projects in the plan

The plan prints no county for this substation, and no utility project page found names one for it.

Projects naming this substation

As the plan prints them. The sponsor is the project’s; one project can split work between owners.

ProjectSponsorWhere in the planNeed dateChange from the previous planSubstations named
GORDON-N DUBLIN 115kV (GORDON-ENGL MCI J) REBUILD
Rebuild approximately 6 miles of the Gordon - North Dublin 115kV line with 200C ACSS 795 conductor.
TEAMS 19618 · plan p.95 · zone 214
GPC In the plan
p.8
Jun 1, 2026 No change Gordon, North Dublin
GTC: GORDON - SANDERSVILLE #1 115kV LINE REBUILD
Rebuild approximately 1.87 miles of the Gordon - Sandersville #1 115kV line with 100C ACSR 795 conductor.
TEAMS 20002 · plan p.110 · zone 214
GTC In the plan
p.9
Dec 1, 2026 No change Gordon, Sandersville
GTC: GORDON-SANDERSVILLE #1 115kV LINE REBUILD (DEEPSTEP-SAND #6)
Rebuild 10.49 miles of the Deepstep - Robins Spring, Robins Spring - Kaolin Jct., and Kaolin Jct. - Sandersville #6 line sections of the Gordon - Sandersville #1 115kV line with 100C ACSR 795 conductor.
TEAMS 20428 · plan p.250 · zone 214
GTC In the plan
p.19
Jun 1, 2030 No change Gordon, Sandersville

Source: 2025 GA ITS Ten-Year Plan (2026-2035), filed by Georgia Power Company as its Annual Transmission Update in Georgia PSC Docket 56002 on February 27, 2026; public disclosure version, retrieved 2026-11-20.