Substation Scout

Forrest Rd

Named in 1 project in the 2025 GA ITS Ten-Year Plan (2026-2035).

—county (not printed)
—kV in the quote
GPCproject sponsor
1projects in the plan

The plan prints no county for this substation, and no utility project page found names one for it.

Projects naming this substation

As the plan prints them. The sponsor is the project’s; one project can split work between owners.

ProjectSponsorWhere in the planNeed dateChange from the previous planSubstations named
ARKWRIGHT BUS AND JUMPER REPLACEMENT
Replace the 115kV bus at Arkwright and replace the jumper on the Arkwright - Forrest Rd (Macon) 115kV line with higher rated equipment.
TEAMS 20767 · plan p.86 · zone 214
GPC In the plan
p.7
Jun 1, 2026 Advanced from 2033 to 2026 Arkwright, Forrest Rd

Source: 2025 GA ITS Ten-Year Plan (2026-2035), filed by Georgia Power Company as its Annual Transmission Update in Georgia PSC Docket 56002 on February 27, 2026; public disclosure version, retrieved 2026-11-20.