Big Tazewell
Named in 2 projects in the 2025 GA ITS Ten-Year Plan (2026-2035).
—county (not printed)
—kV in the quote
GPC, GTCproject sponsor
2projects in the plan
The plan prints no county for this substation, and no utility project page found names one for it.
Projects naming this substation
As the plan prints them. The sponsor is the project’s; one project can split work between owners.
| Project | Sponsor | Where in the plan | Need date | Change from the previous plan | Substations named |
|---|---|---|---|---|---|
| BIG TAZEWELL – PLANT FARLEY (APC) 500kV LINE Construct a new 500kV line from Big Tazewell - Farley (APC) to substation, approximately 120 miles long. Construct a 500kV switching station to loop in the Blacksmith - Talbot 500kV line, terminate the new Farley - Tazewell 500kV and Talbot #2 - Tazewell 500kV lines. TEAMS 21063 · plan p.191 · zone 216 |
GPC | In the plan p.15 |
Jun 1, 2029 | Advanced from 2030 to 2029. | Big Tazewell, Blacksmith, Farley, PLANT FARLEY, Talbot, Tazewell |
| GTC: TALBOT COUNTY 500/230 kV CONVERSION Convert the 230kV Talbot County #1 and Talbot County #2 into a new 500/230kV facility and accommodate the new Big Tazewell - Talbot County 500kV line. TEAMS 21700 · plan p.210 · zone 213 |
GTC | In the plan p.16 |
Jun 1, 2029 | New project | Big Tazewell, Talbot County |
Source: 2025 GA ITS Ten-Year Plan (2026-2035), filed by Georgia Power Company as its Annual Transmission Update in Georgia PSC Docket 56002 on February 27, 2026; public disclosure version, retrieved 2026-11-20.
Before relying on any of this
- The plan prints no county for a substation. A county shown here is printed in the plan beside the station, or on a Georgia Power or Georgia Transmission project page that names the same station and one county.
- Project Sponsor belongs to the project, not to each station; one project can split work between owners.
- Costs are redacted in the public version of the plan and are not shown.