Big Tazewell

Named in 2 projects in the 2025 GA ITS Ten-Year Plan (2026-2035).

—county (not printed)
—kV in the quote
GPC, GTCproject sponsor
2projects in the plan

The plan prints no county for this substation, and no utility project page found names one for it.

Projects naming this substation

As the plan prints them. The sponsor is the project’s; one project can split work between owners.

ProjectSponsorWhere in the planNeed dateChange from the previous planSubstations named
BIG TAZEWELL – PLANT FARLEY (APC) 500kV LINE
Construct a new 500kV line from Big Tazewell - Farley (APC) to substation, approximately 120 miles long. Construct a 500kV switching station to loop in the Blacksmith - Talbot 500kV line, terminate the new Farley - Tazewell 500kV and Talbot #2 - Tazewell 500kV lines.
TEAMS 21063 · plan p.191 · zone 216
GPC In the plan
p.15
Jun 1, 2029 Advanced from 2030 to 2029. Big Tazewell, Blacksmith, Farley, PLANT FARLEY, Talbot, Tazewell
GTC: TALBOT COUNTY 500/230 kV CONVERSION
Convert the 230kV Talbot County #1 and Talbot County #2 into a new 500/230kV facility and accommodate the new Big Tazewell - Talbot County 500kV line.
TEAMS 21700 · plan p.210 · zone 213
GTC In the plan
p.16
Jun 1, 2029 New project Big Tazewell, Talbot County

Source: 2025 GA ITS Ten-Year Plan (2026-2035), filed by Georgia Power Company as its Annual Transmission Update in Georgia PSC Docket 56002 on February 27, 2026; public disclosure version, retrieved 2026-11-20.