Aultman Road
Named in 2 projects in the 2025 GA ITS Ten-Year Plan (2026-2035).
—county (not printed)
—kV in the quote
MEAGproject sponsor
2projects in the plan
The plan prints no county for this substation, and no utility project page found names one for it.
Projects naming this substation
As the plan prints them. The sponsor is the project’s; one project can split work between owners.
| Project | Sponsor | Where in the plan | Need date | Change from the previous plan | Substations named |
|---|---|---|---|---|---|
| MEAG: AULTMAN ROAD - BONAIRE PRIMARY 115 kV REBUILD MEAG: Rebuild the 1.99 miles of Sleepy Hollow - Peach Blossom 115kV line section of the Aultman Road - Bonaire Primary 115kV line with 100C 795 ACSR. GTC: Replace the jumpers at Sleepy Hollow with 1590 AAC. TEAMS 13787 · plan p.102 · zone 214 |
MEAG | In the plan p.8 |
Jun 1, 2026 | Delayed from 2025 to 2026 | Aultman Road, Bonaire Primary, Peach Blossom, Sleepy Hollow |
| MEAG: AULTMAN ROAD - FORT VALLEY #1 115kV REBUILD Rebuild approximately 8 miles of the Aultman Road - Fort Valley #1 115kV line with 200C 1351 ACSS conductor. TEAMS 17706 · plan p.215 · zone 214 |
MEAG | In the plan p.16 |
Jun 1, 2029 | No change | Aultman Road, Fort Valley |
Source: 2025 GA ITS Ten-Year Plan (2026-2035), filed by Georgia Power Company as its Annual Transmission Update in Georgia PSC Docket 56002 on February 27, 2026; public disclosure version, retrieved 2026-11-20.
Before relying on any of this
- The plan prints no county for a substation. A county shown here is printed in the plan beside the station, or on a Georgia Power or Georgia Transmission project page that names the same station and one county.
- Project Sponsor belongs to the project, not to each station; one project can split work between owners.
- Costs are redacted in the public version of the plan and are not shown.