Rice Switch

Named in 1 listed project in ERCOT’s transmission project tracking workbook, in Young County. First named in the release with data as of July 13, 2026.

Youngcounty as printed
138kV
ONCORutility
1projects listed

No HIFLD substation record has this name in this county.

Generation interconnection requests filed in Young, TX: ERCOT queue, 8 active of 11. Same county, not the same substation.

Projects naming this substation

As the utility reported them in the current release. The tab is ERCOT’s; the status is the utility’s.

ProjectUtilityStatus as reportedkVProjected in serviceTerminalsSubstations named
Graham Plant Switch - Rice Switch 138 kV Line
Upgrade Graham Plant Switch - Rice Switch 138 kV Line
ERCOT project 110298 · utility no. M3547
ONCOR
Tier 3
Conceptual
Future tab
138 Jun 2032 Graham Plant Switch to Rice Switch
Young County
Graham Plant Switch, Rice Switch

Changes between releases

Where two consecutive releases print different values for these projects (last ten releases).

Release (data as of)ProjectWhat changedPrinted values
July 13, 2026110298First listedon the Future tab

Source: ERCOT TPIT workbook, data as of October 1, 2026, retrieved 2026-10-26; posting page last checked 2026-11-23. Each row is cited by sheet and row number in the workbook.