Substation Scout

Bowman Switch

Named in 3 listed projects in ERCOT’s transmission project tracking workbook, in Wichita County. First named in the release with data as of June 1, 2016.

Wichitacounty as printed
345kV
ONCORutility
3projects listed

No HIFLD substation record has this name in this county.

Generation interconnection requests filed in Wichita, TX: ERCOT queue, 12 active of 15. Same county, not the same substation.

Projects naming this substation

As the utility reported them in the current release. The tab is ERCOT’s; the status is the utility’s.

ProjectUtilityStatus as reportedkVProjected in serviceTerminalsSubstations named
Oncor_MW_104832_CarolinaStorage_Switch
Establish Switch for Carolina Storage
ERCOT project 104832
ONCOR
Tier 4
Planned
Future tab
345 May 2028 Bowman Switch to Cobb Switch
Wichita County
Bowman Switch, Cobb Switch
Lomond_Switch_345kV
Establish Lomond 345 kV Switch
ERCOT project 105012
ONCOR
Tier 3
Planned
Future tab
345 May 2028 Bowman Switch to Fisher Road Switch
Wichita County
Bowman Switch, Fisher Road Switch
Bowman 345 kV Switch Capacitor Bank
ERCOT project 110178 · utility no. M3568
ONCOR
Tier 4
Conceptual
Future tab
345 Dec 2029 Bowman Switch to Bowman Switch
Wichita County
Bowman Switch

Changes between releases

Where two consecutive releases print different values for these projects (last ten releases).

Release (data as of)ProjectWhat changedPrinted values
October 1, 2026110178Projected in-service dateMay 2028 → Dec 2029
July 13, 2026110178First listedon the Future tab
June 1, 2026104832First listedon the Future tab
June 1, 2026105012First listedon the Future tab

Source: ERCOT TPIT workbook, data as of October 1, 2026, retrieved 2026-10-26; posting page last checked 2026-11-23. Each row is cited by sheet and row number in the workbook.