Gay Hill

Named in 3 listed projects in ERCOT’s transmission project tracking workbook, in Washington County. First named in the release with data as of October 1, 2020.

Washingtoncounty as printed
138kV
BBECutility
3projects listed

No HIFLD substation record has this name in this county.

Generation interconnection requests filed in Washington, TX: ERCOT queue, 0 active of 1. Same county, not the same substation.

Projects naming this substation

As the utility reported them in the current release. The tab is ERCOT’s; the status is the utility’s.

ProjectUtilityStatus as reportedkVProjected in serviceTerminalsSubstations named
BBEC Gay Hill substation high side upgrade
Replace 336 (Linnet) conductor, jumpers, and connectors with 959 (Suwannee) conductor, jumpers, and connectors. (MLSE)
ERCOT project 104599
BBEC
Tier 4
Planned
Future tab
138 Dec 2027 Gay Hill
Washington County
Gay Hill
BBEC Gay Hill to Sandy Hill Transmission Line Upgrade
Replace 336 (Linnet) conductor with 959 (Suwannee) and replace a limited number of structures to accommodate the new conductor.
ERCOT project 104615
BBEC
Tier 4
Planned
Future tab
138 Dec 2030 Gay Hill to Sandy Hill
Washington County
Gay Hill, Sandy Hill
Max Zuehlke_Gay Hill_TL_Upgrade
Replace 336 (Linnet) conductor with 959 (Suwannee) and replace a limited number of structures to accommodate the new conductor.
ERCOT project 91419
BBEC
Tier 4
Planned
Current-year planned tab
138 Dec 2026 Max Zuehlke to Gay Hill
Washington County
Max Zuehlke, Gay Hill

Changes between releases

Where two consecutive releases print different values for these projects (last ten releases).

Release (data as of)ProjectWhat changedPrinted values
June 1, 2026104599First listedon the Future tab
June 1, 2026104615First listedon the Future tab
February 1, 202691419Moved between tabsFuture → Current-year planned
October 1, 202591419Moved between tabsCurrent-year planned → Future
October 1, 202591419Projected in-service dateDec 2025 → Dec 2026
June 1, 202591419First listedon the Current-year planned tab

Source: ERCOT TPIT workbook, data as of October 1, 2026, retrieved 2026-10-26; posting page last checked 2026-11-23. Each row is cited by sheet and row number in the workbook.