Washington, TX interconnection queue

1 active project totalling 208.8 MW in the ERCOT queue.

1active projects
208.8active MW
1total filed
Queue IDProjectkVMWResourceStatus
28INR0095 Starlit Pasture Storage 138 208.8 Battery SS Completed, FIS Started, No IA

Capacity that has left the queue does not automatically become available injection capacity — a withdrawal frees study position. Confirm deliverability with ERCOT before relying on these figures.