MISSION

Named in 3 listed projects in ERCOT’s transmission project tracking workbook, in Waller County. First named in the release with data as of October 1, 2022.

Wallercounty as printed
345kV
CNPutility
3projects listed

Described as new. The quoted wording calls this substation new. “New 345kV Mission (MSS) substation” — project 69902A title, as the utility reported it

Reported complete. Project 69902A is on the Completed tab (actual in-service 2025-05); Project 69902C is on the Completed tab (actual in-service 2025-05), as the utility reported it. That indicates the substation may now be built; it is not a confirmation.

Also printed as: Mission

No HIFLD substation record has this name in this county.

Generation interconnection requests filed in Waller, TX: ERCOT queue, 5 active of 6. Same county, not the same substation.

Location

Waller County, TX

County only. A source prints the county; no point is published. This is where planning documents put the substation, not a surveyed or built site, and a planned site can move.

Note: TPIT 110077A (Conceptual, ISD 2028-07) adds a further new 345 kV substation ('NewSub') looped into the Zenith to Mission circuit for a proposed load; that is a different station.

Sources: ERCOT Transmission Project and Information Tracking (TPIT) workbook, project(s) 69902A, 69902C, 110077A (release 2026-10-01) · PUCT Project 35077, CenterPoint Energy Standard Generation Interconnection Agreement, Parliament Solar (contract INT-21-201A), Exhibit C (2022-05), Exhibit C · OpenStreetMap: unnamed 345 kV yard, operator CenterPoint Energy, beside way 1475139688 (operator Parliament Solar, LLC) (OSM base 2026-11-20). Map data © OpenStreetMap contributors, available under the Open Database License. Researched by Substation Scout; checked November 21, 2026.

Projects naming this substation

As the utility reported them in the current release. The tab is ERCOT’s; the status is the utility’s.

ProjectUtilityStatus as reportedkVProjected in serviceTerminalsSubstations named
This models upgrades required for a proposed load addition.
Install new 345 kV substation (NewSub). Loop into the existing Zenith to Mission ckt. 18.
ERCOT project 110077A
CNP
Tier 4
Conceptual
Future tab
345 Jul 2028 NewSub to Zenith/Mission
Harris / Waller County
Zenith, Mission
New 345kV Mission (MSS) substation for generator interconnection to Parliament Solar.
New 345kV Mission (MSS) substation for generator interconnection to Parliament Solar. Loop Ckt.18E into Mission substation to create new Ckt.18 Gibbons Creek to Mission to Zenith. (Ckt.18 Gibbons Creek to Mission tie-line).
ERCOT project 69902A
CNP
Tier 4
In-Service
Completed tab
345 May 2025
actual 2025-05
MISSION to Gibbons Creek/Zenith
Waller County
MISSION, Gibbons Creek, Zenith
New 345kV Mission (MSS) substation for generator interconnection to Parliament Solar.
Install generator lead from Mission (MSS) substation to Parliament/Parliament Solar
ERCOT project 69902C
CNP
Tier 4
In-Service
Completed tab
345 May 2025
actual 2025-05
MISSION to Parliament
Waller County
MISSION, Parliament

Changes between releases

Where two consecutive releases print different values for these projects (last ten releases).

Release (data as of)ProjectWhat changedPrinted values
July 13, 2026110077AFirst listedon the Future tab
June 1, 202569902AMoved between tabsFuture → Completed
June 1, 202569902AStatus as reportedPlanned → In-Service
June 1, 202569902CMoved between tabsFuture → Completed
June 1, 202569902CStatus as reportedPlanned → In-Service
February 1, 202569902AProjected in-service dateDec 2024 → May 2025
February 1, 202569902CFirst listedon the Future tab
June 1, 202469902AProjected in-service dateMay 2024 → Dec 2024

Source: ERCOT TPIT workbook, data as of October 1, 2026, retrieved 2026-10-26; posting page last checked 2026-11-23. Each row is cited by sheet and row number in the workbook.