MISSION
Named in 3 listed projects in ERCOT’s transmission project tracking workbook, in Waller County. First named in the release with data as of October 1, 2022.
Described as new. The quoted wording calls this substation new. “New 345kV Mission (MSS) substation” — project 69902A title, as the utility reported it
Reported complete. Project 69902A is on the Completed tab (actual in-service 2025-05); Project 69902C is on the Completed tab (actual in-service 2025-05), as the utility reported it. That indicates the substation may now be built; it is not a confirmation.
Also printed as: Mission
No HIFLD substation record has this name in this county.
Generation interconnection requests filed in Waller, TX: ERCOT queue, 5 active of 6. Same county, not the same substation.
Location
Waller County, TX
County only. A source prints the county; no point is published. This is where planning documents put the substation, not a surveyed or built site, and a planned site can move.
Note: TPIT 110077A (Conceptual, ISD 2028-07) adds a further new 345 kV substation ('NewSub') looped into the Zenith to Mission circuit for a proposed load; that is a different station.
Sources: ERCOT Transmission Project and Information Tracking (TPIT) workbook, project(s) 69902A, 69902C, 110077A (release 2026-10-01) · PUCT Project 35077, CenterPoint Energy Standard Generation Interconnection Agreement, Parliament Solar (contract INT-21-201A), Exhibit C (2022-05), Exhibit C · OpenStreetMap: unnamed 345 kV yard, operator CenterPoint Energy, beside way 1475139688 (operator Parliament Solar, LLC) (OSM base 2026-11-20). Map data © OpenStreetMap contributors, available under the Open Database License. Researched by Substation Scout; checked November 21, 2026.
Projects naming this substation
As the utility reported them in the current release. The tab is ERCOT’s; the status is the utility’s.
| Project | Utility | Status as reported | kV | Projected in service | Terminals | Substations named |
|---|---|---|---|---|---|---|
| This models upgrades required for a proposed load addition. Install new 345 kV substation (NewSub). Loop into the existing Zenith to Mission ckt. 18. ERCOT project 110077A |
CNP Tier 4 |
Conceptual Future tab |
345 | Jul 2028 | NewSub to Zenith/Mission Harris / Waller County |
Zenith, Mission |
| New 345kV Mission (MSS) substation for generator interconnection to Parliament Solar. New 345kV Mission (MSS) substation for generator interconnection to Parliament Solar. Loop Ckt.18E into Mission substation to create new Ckt.18 Gibbons Creek to Mission to Zenith. (Ckt.18 Gibbons Creek to Mission tie-line). ERCOT project 69902A |
CNP Tier 4 |
In-Service Completed tab |
345 | May 2025 actual 2025-05 |
MISSION to Gibbons Creek/Zenith Waller County |
MISSION, Gibbons Creek, Zenith |
| New 345kV Mission (MSS) substation for generator interconnection to Parliament Solar. Install generator lead from Mission (MSS) substation to Parliament/Parliament Solar ERCOT project 69902C |
CNP Tier 4 |
In-Service Completed tab |
345 | May 2025 actual 2025-05 |
MISSION to Parliament Waller County |
MISSION, Parliament |
Changes between releases
Where two consecutive releases print different values for these projects (last ten releases).
| Release (data as of) | Project | What changed | Printed values |
|---|---|---|---|
| July 13, 2026 | 110077A | First listed | on the Future tab |
| June 1, 2025 | 69902A | Moved between tabs | Future → Completed |
| June 1, 2025 | 69902A | Status as reported | Planned → In-Service |
| June 1, 2025 | 69902C | Moved between tabs | Future → Completed |
| June 1, 2025 | 69902C | Status as reported | Planned → In-Service |
| February 1, 2025 | 69902A | Projected in-service date | Dec 2024 → May 2025 |
| February 1, 2025 | 69902C | First listed | on the Future tab |
| June 1, 2024 | 69902A | Projected in-service date | May 2024 → Dec 2024 |
Source: ERCOT TPIT workbook, data as of October 1, 2026, retrieved 2026-10-26; posting page last checked 2026-11-23. Each row is cited by sheet and row number in the workbook.
Before relying on any of this
- TPIT lists substation work only where it changes a transmission line or autotransformer rating. A new load-serving substation that changes no rating may never appear in it.
- Every value is the Transmission Service Provider's own statement, compiled by ERCOT. Status and in-service dates are not ERCOT determinations.
- The workbook tab (Future, Current-year planned, Completed, Cancelled) is assigned by ERCOT from dates; the status column is the TSP's word. The two can disagree, and both are shown.
- In ERCOT's competitive areas the company named is the transmission and distribution wires company, not a retail electricity provider or a generator.
- ERCOT publishes the workbook about three times a year, plus occasional updates. A substation that is not listed may simply not be reported yet.
- Substation names are read from the workbook's "from" and "to" terminal columns; for rows with neither, from fixed patterns in the title and description. No language model reads this workbook.
- An entry is a name within a county, not a verified physical facility. A link to a HIFLD record means the names and counties agree exactly, not that the two are confirmed to be one facility.