Substation Scout

Shepley

Named in 1 listed project in ERCOT’s transmission project tracking workbook, in Victoria County. First named in the release with data as of October 1, 2023.

Victoriacounty as printed
138kV
AEP TCCutility
1projects listed

No HIFLD substation record has this name in this county.

Generation interconnection requests filed in Victoria, TX: ERCOT queue, 17 active of 22. Same county, not the same substation.

Projects naming this substation

As the utility reported them in the current release. The tab is ERCOT’s; the status is the utility’s.

ProjectUtilityStatus as reportedkVProjected in serviceTerminalsSubstations named
Shepley: Construct New Distribution Station
Construct new distribution station on the Victoria to Dupont Switch 138 kV line
ERCOT project 69489
AEP TCC
Tier 4
Under Construction
Current-year planned tab
138 Nov 2026 Shepley
Victoria County
Shepley

Changes between releases

Where two consecutive releases print different values for these projects (last ten releases).

Release (data as of)ProjectWhat changedPrinted values
October 1, 202669489Projected in-service dateJul 2026 → Nov 2026
June 1, 202669489Projected in-service dateApr 2026 → Jul 2026
February 1, 202669489Moved between tabsFuture → Current-year planned
February 1, 202669489Projected in-service dateFeb 2026 → Apr 2026
February 1, 202569489Status as reportedPlanned → Under Construction
June 1, 202469489Projected in-service dateMar 2025 → Feb 2026

Source: ERCOT TPIT workbook, data as of October 1, 2026, retrieved 2026-10-26; posting page last checked 2026-11-23. Each row is cited by sheet and row number in the workbook.

Before relying on any of this

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first