Named in 1 listed project in ERCOT’s transmission project tracking workbook, in Victoria County. First named in the release with data as of October 1, 2025.

Victoriacounty as printed
138kV
AEP TCCutility
1projects listed

Expansion at an existing substation: new or expanded yard. The quoted wording describes a new or expanded yard, bus, bay or station at this substation. “Expand 138 kV Station” — project 98798, as the utility reported it

No HIFLD substation record has this name in this county.

Generation interconnection requests filed in Victoria, TX: ERCOT queue, 17 active of 22. Same county, not the same substation.

Projects naming this substation

As the utility reported them in the current release. The tab is ERCOT’s; the status is the utility’s.

ProjectUtilityStatus as reportedkVProjected in serviceTerminalsSubstations named
Beecher: Expand 138 kV Station
Interconnect Leopard BESS to the existing Beecher 138 kV station
ERCOT project 98798 · utility no. TP2025255
AEP TCC
Tier 4
Planned
Future tab
138 Feb 2028 Beecher
Victoria County
Beecher

Changes between releases

Where two consecutive releases print different values for these projects (last ten releases).

Release (data as of)ProjectWhat changedPrinted values
October 1, 202598798First listedon the Future tab

Source: ERCOT TPIT workbook, data as of October 1, 2026, retrieved 2026-10-26; posting page last checked 2026-11-23. Each row is cited by sheet and row number in the workbook.