Hamilton Road

Named in 3 listed projects in ERCOT’s transmission project tracking workbook, in Val Verde County. First named in the release with data as of February 1, 2015.

Val Verdecounty as printed
138kV
AEP TCC, AEP TCC/ETTutility
3projects listed

No HIFLD substation record has this name in this county.

Generation interconnection requests filed in Val Verde, TX: ERCOT queue, 3 active of 5. Same county, not the same substation.

Projects naming this substation

As the utility reported them in the current release. The tab is ERCOT’s; the status is the utility’s.

ProjectUtilityStatus as reportedkVProjected in serviceTerminalsSubstations named
Ganso to Hamilton Road: Rebuild 138 kV line
Rebuild 138 kV line from Ganso to Hamilton Road
ERCOT project 55626 · utility no. 3824 · RPG 22RPG044
AEP TCC
Tier 3
Planned
Future tab
138 Sep 2028 Maverick to Hamilton Road
Maverick / Val Verde County
Maverick, Hamilton Road
Hamilton Road to Maxwell: Rebuild 138 kV Line
Rebuild the Hamilton Road to Maxwell 138 kV line
ERCOT project 61396 · utility no. TA2019800 · RPG 20RPG022
AEP TCC
Tier 3
Planned
Current-year planned tab
138 Nov 2026 Hamilton Road to Maxwell
Val Verde County
Hamilton Road, Maxwell
Hamilton Road: Construct New 138 kV Terminal
Interconnect Tierra Seca BESS to the Hamilton Road 138 kV station
ERCOT project 76274 · utility no. TP2023133
AEP TCC/ETT
Tier 4
In-Service
Completed tab
138 Oct 2025
actual 2025-10
Hamilton Road
Val Verde County
Hamilton Road

Changes between releases

Where two consecutive releases print different values for these projects (last ten releases).

Release (data as of)ProjectWhat changedPrinted values
October 1, 202655626Projected in-service dateFeb 2028 → Sep 2028
February 1, 202661396Moved between tabsFuture → Current-year planned
February 1, 202676274Moved between tabsCurrent-year planned → Completed
February 1, 202676274Status as reportedUnder Construction → In-Service
October 1, 202576274Projected in-service dateMay 2025 → Oct 2025
June 1, 202576274Moved between tabsFuture → Current-year planned
June 1, 202576274Status as reportedPlanned → Under Construction
June 1, 202455626Projected in-service dateDec 2026 → Feb 2028
June 1, 202461396Projected in-service dateNov 2024 → Nov 2026

Source: ERCOT TPIT workbook, data as of October 1, 2026, retrieved 2026-10-26; posting page last checked 2026-11-23. Each row is cited by sheet and row number in the workbook.