Poblano
Named in 2 listed projects in ERCOT’s transmission project tracking workbook, in Uvalde County. First named in the release with data as of October 1, 2023.
Described as new. The quoted wording calls this substation new. “Poblano: Build new 138 kV station” — project 76580 title, as the utility reported it
No HIFLD substation record has this name in this county.
Generation interconnection requests filed in Uvalde, TX: ERCOT queue, 3 active of 11. Same county, not the same substation.
Location
Uvalde County, TX
County only. A source prints the county; no point is published. This is where planning documents put the substation, not a surveyed or built site, and a planned site can move.
Note: DOE (Oct 2026) calls Poblano 'the existing Poblano Station'; TPIT 76580 is Under Construction with ISD 2027-04. Poblano may be energized or partly built; not confirmed.
Sources: ERCOT Transmission Project and Information Tracking (TPIT) workbook, project(s) 76580, 87648 (release 2026-10-01) · US DOE Office of Energy Dominance Financing, completion of environmental review, La Pryor to Poblano Transmission Line Project, Uvalde County (2026-10-20), p.1. Researched by Substation Scout; checked November 21, 2026.
Projects naming this substation
As the utility reported them in the current release. The tab is ERCOT’s; the status is the utility’s.
| Project | Utility | Status as reported | kV | Projected in service | Terminals | Substations named |
|---|---|---|---|---|---|---|
| Poblano: Build new 138 kV station Convert Asherton to Uvalde 69 kV to 138 kV, rebuild Asherton 138 kV station, build new Poblano 138 kV station ERCOT project 76580 · RPG 23RPG007 |
AEP TCC Tier 3 |
Under Construction Future tab |
138 | Apr 2027 | Poblano Uvalde County |
Poblano |
| Carver to Poblano: Convert 69 kV Line to 138 kV Convert the Sonora to Uvalde 69 kV line to 138 kV and reterminate at Carver and Poblano ERCOT project 87648 · utility no. TP2024058 · RPG 24RPG009 |
AEP TCC/AEP TNC, ETT Tier 4 |
Planned Future tab |
138 | Jan 2031 | Carver to Poblano Sutton / Uvalde County |
Carver, Poblano |
Changes between releases
Where two consecutive releases print different values for these projects (last ten releases).
| Release (data as of) | Project | What changed | Printed values |
|---|---|---|---|
| October 1, 2026 | 76580 | Status as reported | Planned → Under Construction |
| October 1, 2026 | 87648 | Projected in-service date | Dec 2028 → Jan 2031 |
| February 1, 2026 | 76580 | Projected in-service date | Dec 2026 → Apr 2027 |
| February 1, 2025 | 76580 | Projected in-service date | May 2026 → Dec 2026 |
| October 1, 2024 | 87648 | First listed | on the Future tab |
Source: ERCOT TPIT workbook, data as of October 1, 2026, retrieved 2026-10-26; posting page last checked 2026-11-23. Each row is cited by sheet and row number in the workbook.
Before relying on any of this
- TPIT lists substation work only where it changes a transmission line or autotransformer rating. A new load-serving substation that changes no rating may never appear in it.
- Every value is the Transmission Service Provider's own statement, compiled by ERCOT. Status and in-service dates are not ERCOT determinations.
- The workbook tab (Future, Current-year planned, Completed, Cancelled) is assigned by ERCOT from dates; the status column is the TSP's word. The two can disagree, and both are shown.
- In ERCOT's competitive areas the company named is the transmission and distribution wires company, not a retail electricity provider or a generator.
- ERCOT publishes the workbook about three times a year, plus occasional updates. A substation that is not listed may simply not be reported yet.
- Substation names are read from the workbook's "from" and "to" terminal columns; for rows with neither, from fixed patterns in the title and description. No language model reads this workbook.
- An entry is a name within a county, not a verified physical facility. A link to a HIFLD record means the names and counties agree exactly, not that the two are confirmed to be one facility.