Named in 1 listed project in ERCOT’s transmission project tracking workbook, in Upton County. First named in the release with data as of February 1, 2026.

Uptoncounty as printed
345kV
GPLutility
1projects listed

No HIFLD substation record has this name in this county.

Generation interconnection requests filed in Upton, TX: ERCOT queue, 18 active of 22. Same county, not the same substation.

Projects naming this substation

As the utility reported them in the current release. The tab is ERCOT’s; the status is the utility’s.

ProjectUtilityStatus as reportedkVProjected in serviceTerminalsSubstations named
Bakersfield_NevillRoad_NorthMcCamey_Transmission_Line_Upgrade
PL and LCRA joint PBRP_L14 project by upgrading of the existing Bakersfield - Nevill Road - North McCamey 345kV transmission lines and adding of new 345kV Bakersfield - Nevill Road - North McCamey second circuits
ERCOT project 102795 · utility no. PBRP_L14_Joint
GPL
Tier 1
Planned
Future tab
345 May 2030 Nevill Road to Bakersfield/North McCamey
Upton / Pecos County
Nevill Road, Bakersfield, North McCamey

Changes between releases

Where two consecutive releases print different values for these projects (last ten releases).

Release (data as of)ProjectWhat changedPrinted values
February 1, 2026102795First listedon the Future tab

Source: ERCOT TPIT workbook, data as of October 1, 2026, retrieved 2026-10-26; posting page last checked 2026-11-23. Each row is cited by sheet and row number in the workbook.