Named in 1 listed project in ERCOT’s transmission project tracking workbook, in Travis County. First named in the release with data as of February 1, 2015.

Traviscounty as printed
138kV
AENutility
1projects listed

No HIFLD substation record has this name in this county.

Generation interconnection requests filed in Travis, TX: ERCOT queue, 8 active of 8. Same county, not the same substation.

Projects naming this substation

As the utility reported them in the current release. The tab is ERCOT’s; the status is the utility’s.

ProjectUtilityStatus as reportedkVProjected in serviceTerminalsSubstations named
East_Village138kV Substation
East_Village 138kV Substation
ERCOT project 11TPIT0011
AEN
Tier 4
In-Service
Completed tab
138 Jun 2025
actual 2025-05
Techridge to East_Village SUB
Travis County
Techridge

Changes between releases

Where two consecutive releases print different values for these projects (last ten releases).

Release (data as of)ProjectWhat changedPrinted values
October 1, 202511TPIT0011Status as reportedPlanned → In-Service
June 1, 202511TPIT0011Moved between tabsFuture → Completed
October 1, 202411TPIT0011Projected in-service dateOct 2024 → Jun 2025

Source: ERCOT TPIT workbook, data as of October 1, 2026, retrieved 2026-10-26; posting page last checked 2026-11-23. Each row is cited by sheet and row number in the workbook.