Substation Scout

Southshore

Named in 1 listed project in ERCOT’s transmission project tracking workbook, in Travis County. First named in the release with data as of October 1, 2024.

Traviscounty as printed
138kV
AENutility
1projects listed

No HIFLD substation record has this name in this county.

Generation interconnection requests filed in Travis, TX: ERCOT queue, 8 active of 8. Same county, not the same substation.

Projects naming this substation

As the utility reported them in the current release. The tab is ERCOT’s; the status is the utility’s.

ProjectUtilityStatus as reportedkVProjected in serviceTerminalsSubstations named
AEN_New_138kV_Southshore_Substation_Addition
ERCOT project 86327
AEN
Tier 4
Planned
Future tab
138 Jun 2033 9179 to 9132
Travis County
Southshore

Changes between releases

Where two consecutive releases print different values for these projects (last ten releases).

Release (data as of)ProjectWhat changedPrinted values
July 13, 202686327Projected in-service dateJun 2029 → Jun 2033
June 1, 202686327Projected in-service dateSep 2027 → Jun 2029
October 1, 202486327First listedon the Future tab

Source: ERCOT TPIT workbook, data as of October 1, 2026, retrieved 2026-10-26; posting page last checked 2026-11-23. Each row is cited by sheet and row number in the workbook.

Before relying on any of this

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first