Substation Scout

Lakeway

Named in 1 listed project in ERCOT’s transmission project tracking workbook, in Travis County. First named in the release with data as of June 1, 2018.

Traviscounty as printed
138kV
LCRATSCutility
1projects listed

A HIFLD substation record has the same name and county: LAKEWAY (TRAVIS County). The names agree; that does not confirm they are the same facility.

Generation interconnection requests filed in Travis, TX: ERCOT queue, 8 active of 8. Same county, not the same substation.

Projects naming this substation

As the utility reported them in the current release. The tab is ERCOT’s; the status is the utility’s.

ProjectUtilityStatus as reportedkVProjected in serviceTerminalsSubstations named
Lakeway - Marble Falls Transmission Line Storm Hardening
Increase the reliability of transmission facilities on the T497 Lakeway - Marble Falls 23-mile 138-kV transmission line.
ERCOT project 62068 · RPG 22RPG031
LCRATSC
Tier 4
Planned
Completed tab
138 May 2025
actual 2025-05
Lakeway to Marble Falls
Travis / Burnet County
Lakeway, Marble Falls

Changes between releases

Where two consecutive releases print different values for these projects (last ten releases).

Release (data as of)ProjectWhat changedPrinted values
October 1, 202562068Moved between tabsCurrent-year planned → Completed
October 1, 202562068Projected in-service dateJun 2025 → May 2025
June 1, 202562068Moved between tabsFuture → Current-year planned
February 1, 202562068Projected in-service dateMay 2025 → Jun 2025

Source: ERCOT TPIT workbook, data as of October 1, 2026, retrieved 2026-10-26; posting page last checked 2026-11-23. Each row is cited by sheet and row number in the workbook.