Cedar Valley
Named in 2 listed projects in ERCOT’s transmission project tracking workbook, in Travis County. First named in the release with data as of June 1, 2021.
A HIFLD substation record has the same name and county: CEDAR VALLEY (TRAVIS County). The names agree; that does not confirm they are the same facility.
Generation interconnection requests filed in Travis, TX: ERCOT queue, 8 active of 8. Same county, not the same substation.
Projects naming this substation
As the utility reported them in the current release. The tab is ERCOT’s; the status is the utility’s.
| Project | Utility | Status as reported | kV | Projected in service | Terminals | Substations named |
|---|---|---|---|---|---|---|
| Cedar Valley to Friendship Storm Hardening Rebuild single circuit section of Cedar Valley to Friendship and reconductor with bundled 795 ACSR Conductor, 440 MVA. Replaces Project ID 61268 ERCOT project 72566 |
PEC Tier 4 |
Planned Completed tab |
138 | Nov 2025 actual 2025-05 |
Cedar Valley to Friendship Travis County |
Cedar Valley, Friendship |
| Trading Post to Cedar Valley Storm Hardening ERCOT project 72588A |
PEC Tier 4 |
Planned Completed tab |
138 | May 2025 actual 2025-05 |
Trading Post to Cedar Valley Travis County |
Trading Post, Cedar Valley |
Changes between releases
Where two consecutive releases print different values for these projects (last ten releases).
| Release (data as of) | Project | What changed | Printed values |
|---|---|---|---|
| October 1, 2026 | 72566 | Moved between tabs | Current-year planned → Completed |
| June 1, 2025 | 72566 | Moved between tabs | Future → Current-year planned |
| June 1, 2025 | 72588A | Moved between tabs | Future → Completed |
| October 1, 2024 | 72588A | First listed | on the Future tab |
Source: ERCOT TPIT workbook, data as of October 1, 2026, retrieved 2026-10-26; posting page last checked 2026-11-23. Each row is cited by sheet and row number in the workbook.
Before relying on any of this
- TPIT lists substation work only where it changes a transmission line or autotransformer rating. A new load-serving substation that changes no rating may never appear in it.
- Every value is the Transmission Service Provider's own statement, compiled by ERCOT. Status and in-service dates are not ERCOT determinations.
- The workbook tab (Future, Current-year planned, Completed, Cancelled) is assigned by ERCOT from dates; the status column is the TSP's word. The two can disagree, and both are shown.
- In ERCOT's competitive areas the company named is the transmission and distribution wires company, not a retail electricity provider or a generator.
- ERCOT publishes the workbook about three times a year, plus occasional updates. A substation that is not listed may simply not be reported yet.
- Substation names are read from the workbook's "from" and "to" terminal columns; for rows with neither, from fixed patterns in the title and description. No language model reads this workbook.
- An entry is a name within a county, not a verified physical facility. A link to a HIFLD record means the names and counties agree exactly, not that the two are confirmed to be one facility.