Named in 1 listed project in ERCOT’s transmission project tracking workbook, in Tom Green County. First named in the release with data as of February 1, 2015.

Tom Greencounty as printed
138kV
LCRATSCutility
1projects listed

A HIFLD substation record has the same name and county: TWIN BUTTES (TOM GREEN County). The names agree; that does not confirm they are the same facility.

Generation interconnection requests filed in Tom Green, TX: ERCOT queue, 13 active of 13. Same county, not the same substation.

Projects naming this substation

As the utility reported them in the current release. The tab is ERCOT’s; the status is the utility’s.

ProjectUtilityStatus as reportedkVProjected in serviceTerminalsSubstations named
Twin Buttes Load 138-KV Circuit Breaker Addition
Provide a 138-kV point of interconnection at the Twin Buttes Substation to connect to a new Golden Spread Electric Cooperative Transmission line. Update contingencies
ERCOT project 71950
LCRATSC
Tier 4
Planned
Current-year planned tab
138 Oct 2026 Twin Buttes
Tom Green County
Twin Buttes

Changes between releases

Where two consecutive releases print different values for these projects (last ten releases).

Release (data as of)ProjectWhat changedPrinted values
July 13, 202671950Projected in-service dateMay 2026 → Oct 2026
February 1, 202671950Moved between tabsFuture → Current-year planned
October 1, 202571950Moved between tabsCurrent-year planned → Future
October 1, 202571950Projected in-service dateSep 2025 → May 2026
June 1, 202571950Moved between tabsFuture → Current-year planned
October 1, 202471950Projected in-service dateDec 2024 → Sep 2025

Source: ERCOT TPIT workbook, data as of October 1, 2026, retrieved 2026-10-26; posting page last checked 2026-11-23. Each row is cited by sheet and row number in the workbook.