Named in 1 listed project in ERCOT’s transmission project tracking workbook, in Tom Green County. First named in the release with data as of October 1, 2021.

Tom Greencounty as printed
138kV
AEP TNCutility
1projects listed

No HIFLD substation record has this name in this county.

Generation interconnection requests filed in Tom Green, TX: ERCOT queue, 13 active of 13. Same county, not the same substation.

Projects naming this substation

As the utility reported them in the current release. The tab is ERCOT’s; the status is the utility’s.

ProjectUtilityStatus as reportedkVProjected in serviceTerminalsSubstations named
Tribute: Build 138 kV Station
Build new 138 kV Station on the San Angelo Power to Red Creek 138 kV line
ERCOT project 63635 · utility no. 1877
AEP TNC
Tier 4
Planned
Future tab
138 May 2027 Tribute
Tom Green County
Tribute

Changes between releases

Where two consecutive releases print different values for these projects (last ten releases).

Release (data as of)ProjectWhat changedPrinted values
June 1, 202663635Moved between tabsCurrent-year planned → Future
June 1, 202663635Projected in-service dateJan 2026 → May 2027
February 1, 202663635Projected in-service dateNov 2025 → Jan 2026
October 1, 202563635Projected in-service dateMay 2025 → Nov 2025
June 1, 202563635Moved between tabsFuture → Current-year planned
February 1, 202563635Projected in-service dateNov 2024 → May 2025
June 1, 202463635Projected in-service dateJun 2024 → Nov 2024

Source: ERCOT TPIT workbook, data as of October 1, 2026, retrieved 2026-10-26; posting page last checked 2026-11-23. Each row is cited by sheet and row number in the workbook.