Mulberry Creek

Named in 1 listed project in ERCOT’s transmission project tracking workbook, in Taylor County. First named in the release with data as of July 13, 2026.

Taylorcounty as printed
345kV
AEP TNCutility
1projects listed

Expansion at an existing substation: new or expanded yard. The quoted wording describes a new or expanded yard, bus, bay or station at this substation. “Expand 345 kV Station” — project 109743, as the utility reported it

A project here also describes a named load connected: “Interconnect the Lancium load to the Mulberry Creek 345 kV station” (project 109743)

No HIFLD substation record has this name in this county.

Generation interconnection requests filed in Taylor, TX: ERCOT queue, 13 active of 15. Same county, not the same substation.

Projects naming this substation

As the utility reported them in the current release. The tab is ERCOT’s; the status is the utility’s.

ProjectUtilityStatus as reportedkVProjected in serviceTerminalsSubstations named
Mulberry Creek: Expand 345 kV Station
Interconnect the Lancium load to the Mulberry Creek 345 kV station
ERCOT project 109743 · utility no. TP2026091
AEP TNC
Tier 4
Planned
Future tab
345 Dec 2028 Mulberry Creek
Taylor County
Mulberry Creek

Changes between releases

Where two consecutive releases print different values for these projects (last ten releases).

Release (data as of)ProjectWhat changedPrinted values
July 13, 2026109743First listedon the Future tab

Source: ERCOT TPIT workbook, data as of October 1, 2026, retrieved 2026-10-26; posting page last checked 2026-11-23. Each row is cited by sheet and row number in the workbook.

Before relying on any of this

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first