Abilene South
Named in 1 listed project in ERCOT’s transmission project tracking workbook, in Taylor County. First named in the release with data as of February 1, 2015.
A HIFLD substation record has the same name and county: ABILENE SOUTH (TAYLOR County). The names agree; that does not confirm they are the same facility.
Generation interconnection requests filed in Taylor, TX: ERCOT queue, 13 active of 15. Same county, not the same substation.
Projects naming this substation
As the utility reported them in the current release. The tab is ERCOT’s; the status is the utility’s.
| Project | Utility | Status as reported | kV | Projected in service | Terminals | Substations named |
|---|---|---|---|---|---|---|
| Abilene South to Estes: Rebuild 138 kV Line Rehab Abilene South to structure 33/7 ERCOT project 68150 |
AEP TNC Tier 4 |
In-Service Completed tab |
138 | Feb 2026 actual 2025-12 |
Abilene South to Estes Taylor / Callahan County |
Abilene South, Estes |
Changes between releases
Where two consecutive releases print different values for these projects (last ten releases).
| Release (data as of) | Project | What changed | Printed values |
|---|---|---|---|
| July 13, 2026 | 68150 | Status as reported | Under Construction → In-Service |
| June 1, 2026 | 68150 | Moved between tabs | Current-year planned → Completed |
| February 1, 2026 | 68150 | Moved between tabs | Future → Current-year planned |
| October 1, 2025 | 68150 | Moved between tabs | Current-year planned → Future |
| October 1, 2025 | 68150 | Projected in-service date | Dec 2025 → Feb 2026 |
| June 1, 2025 | 68150 | Moved between tabs | Future → Current-year planned |
| October 1, 2024 | 68150 | Projected in-service date | Dec 2024 → Dec 2025 |
Source: ERCOT TPIT workbook, data as of October 1, 2026, retrieved 2026-10-26; posting page last checked 2026-11-23. Each row is cited by sheet and row number in the workbook.
Before relying on any of this
- TPIT lists substation work only where it changes a transmission line or autotransformer rating. A new load-serving substation that changes no rating may never appear in it.
- Every value is the Transmission Service Provider's own statement, compiled by ERCOT. Status and in-service dates are not ERCOT determinations.
- The workbook tab (Future, Current-year planned, Completed, Cancelled) is assigned by ERCOT from dates; the status column is the TSP's word. The two can disagree, and both are shown.
- In ERCOT's competitive areas the company named is the transmission and distribution wires company, not a retail electricity provider or a generator.
- ERCOT publishes the workbook about three times a year, plus occasional updates. A substation that is not listed may simply not be reported yet.
- Substation names are read from the workbook's "from" and "to" terminal columns; for rows with neither, from fixed patterns in the title and description. No language model reads this workbook.
- An entry is a name within a county, not a verified physical facility. A link to a HIFLD record means the names and counties agree exactly, not that the two are confirmed to be one facility.