Substation Scout

Fort Griffin

Named in 1 listed project in ERCOT’s transmission project tracking workbook, in Shackelford County. First named in the release with data as of June 1, 2019.

Shackelfordcounty as printed
69kV
AEP TNCutility
1projects listed

No HIFLD substation record has this name in this county.

Generation interconnection requests filed in Shackelford, TX: ERCOT queue, 2 active of 3. Same county, not the same substation.

Projects naming this substation

As the utility reported them in the current release. The tab is ERCOT’s; the status is the utility’s.

ProjectUtilityStatus as reportedkVProjected in serviceTerminalsSubstations named
Belknap to Fort Griffin: Rebuild 69 kV Line
Rehab Belknap to Fort Griffin 69 kV line
ERCOT project 70349 · RPG 22RPG020
AEP TNC
Tier 4
In-Service
Completed tab
69 Jun 2025
actual 2025-06
Belknap to Fort Griffin
Jones / Shackelford County
Belknap, Fort Griffin

Changes between releases

Where two consecutive releases print different values for these projects (last ten releases).

Release (data as of)ProjectWhat changedPrinted values
February 1, 202670349Moved between tabsCurrent-year planned → Completed
February 1, 202670349Status as reportedPlanned → In-Service
October 1, 202570349Projected in-service dateMay 2025 → Jun 2025
June 1, 202570349Moved between tabsFuture → Current-year planned
June 1, 202570349Projected in-service dateOct 2025 → May 2025
October 1, 202470349Projected in-service dateMay 2025 → Oct 2025

Source: ERCOT TPIT workbook, data as of October 1, 2026, retrieved 2026-10-26; posting page last checked 2026-11-23. Each row is cited by sheet and row number in the workbook.

Before relying on any of this

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first