Shackelford, TX interconnection queue

2 active projects totalling 410.4 MW in the ERCOT queue, plus 1 with terminal status (shown greyed).

2active projects
410.4active MW
3total filed
Queue IDProjectkVMWResourceStatus
26INR0282 Haute Stockage n/r 307.3 Battery Inactive
26INR0500 Shackleford BESS 345 206.5 Battery SS Completed, FIS Started, No IA
28INR0151 Chimney Creek Solar 345 203.9 Solar SS Completed, FIS Started, No IA

A request with terminal status left the queue as filed. That is a record of the filing, not evidence of injection capacity at this location. Confirm deliverability with ERCOT before relying on these figures.