Angstrom
Named in 4 listed projects in ERCOT’s transmission project tracking workbook, in San Patricio County. First named in the release with data as of October 1, 2019.
Expansion at an existing substation: new or expanded yard. The quoted wording describes a new or expanded yard, bus, bay or station at this substation. “Expand 345 kV Station” — project 111221, as the utility reported it
A project here also describes a named load connected: “Interconnect the Ripper Industrial load to the existing Angstrom 345 kV station” (project 111221)
No HIFLD substation record has this name in this county.
Generation interconnection requests filed in San Patricio, TX: ERCOT queue, 27 active of 28. Same county, not the same substation.
Projects naming this substation
As the utility reported them in the current release. The tab is ERCOT’s; the status is the utility’s.
| Project | Utility | Status as reported | kV | Projected in service | Terminals | Substations named |
|---|---|---|---|---|---|---|
| Carnelian: Construct New 345 kV Station Interconnect the Somerset Rebel load to the new Carnelian 345 kV station on the Whitepoint to Angstrom 345 kV line ERCOT project 109704 · utility no. TP2026075 |
AEP TCC Tier 4 |
Planned Future tab |
345 | Oct 2028 | Angstrom to White point San Patricio County |
Angstrom, White point |
| Angstrom: Expand 345 kV Station Interconnect the Ripper Industrial load to the existing Angstrom 345 kV station ERCOT project 111221 · utility no. TP2026123 |
AEP TCC Tier 4 |
Planned Future tab |
345 | Jul 2029 | Angstrom San Patricio County |
Angstrom |
| Angstrom: Construct New 345 kV Terminal Interconnect Pintail Pass BESS to the Angstrom 345 kV station ERCOT project 76194 · utility no. TP2023132 |
AEP TCC Tier 4 |
In-Service Completed tab |
345 | Jan 2026 actual 2026-01 |
Angstrom San Patricio County |
Angstrom |
| Angstrom to STP: Increase 345 kV Line MOT Increase the MOT on the Angstrom to STP 345 kV line ERCOT project 80630 |
AEP TCC Tier 4 |
Under Construction Current-year planned tab |
345 | Nov 2026 | Angstrom to STP San Patricio / Matagorda County |
Angstrom, STP |
Changes between releases
Where two consecutive releases print different values for these projects (last ten releases).
| Release (data as of) | Project | What changed | Printed values |
|---|---|---|---|
| October 1, 2026 | 111221 | First listed | on the Future tab |
| October 1, 2026 | 80630 | Projected in-service date | Jun 2026 → Nov 2026 |
| July 13, 2026 | 109704 | First listed | on the Future tab |
| July 13, 2026 | 80630 | Projected in-service date | May 2026 → Jun 2026 |
| June 1, 2026 | 76194 | Moved between tabs | Current-year planned → Completed |
| June 1, 2026 | 76194 | Status as reported | Planned → In-Service |
| June 1, 2026 | 80630 | Projected in-service date | Jan 2026 → May 2026 |
| February 1, 2026 | 76194 | Projected in-service date | Nov 2025 → Jan 2026 |
| February 1, 2026 | 80630 | Status as reported | Planned → Under Construction |
| February 1, 2026 | 80630 | Projected in-service date | Dec 2025 → Jan 2026 |
| October 1, 2025 | 76194 | Projected in-service date | May 2025 → Nov 2025 |
| June 1, 2025 | 76194 | Moved between tabs | Future → Current-year planned |
| June 1, 2025 | 80630 | Moved between tabs | Future → Current-year planned |
| October 1, 2024 | 76194 | Status as reported | Conceptual → Planned |
| June 1, 2024 | 80630 | First listed | on the Future tab |
Source: ERCOT TPIT workbook, data as of October 1, 2026, retrieved 2026-10-26; posting page last checked 2026-11-23. Each row is cited by sheet and row number in the workbook.
Before relying on any of this
- TPIT lists substation work only where it changes a transmission line or autotransformer rating. A new load-serving substation that changes no rating may never appear in it.
- Every value is the Transmission Service Provider's own statement, compiled by ERCOT. Status and in-service dates are not ERCOT determinations.
- The workbook tab (Future, Current-year planned, Completed, Cancelled) is assigned by ERCOT from dates; the status column is the TSP's word. The two can disagree, and both are shown.
- In ERCOT's competitive areas the company named is the transmission and distribution wires company, not a retail electricity provider or a generator.
- ERCOT publishes the workbook about three times a year, plus occasional updates. A substation that is not listed may simply not be reported yet.
- Substation names are read from the workbook's "from" and "to" terminal columns; for rows with neither, from fixed patterns in the title and description. No language model reads this workbook.
- An entry is a name within a county, not a verified physical facility. A link to a HIFLD record means the names and counties agree exactly, not that the two are confirmed to be one facility.