Anastase
Named in 1 listed project in ERCOT’s transmission project tracking workbook, in Runnels County. First named in the release with data as of October 1, 2025.
Described as new. The quoted wording calls this substation new. “Anastase: Construct New 138 kV Station” — project 99540 title, as the utility reported it
No HIFLD substation record has this name in this county.
Generation interconnection requests filed in Runnels, TX: ERCOT queue, 8 active of 8. Same county, not the same substation.
Location
Runnels County, TX
On a named line, no point. No point is published. The planning documents place it on the transmission line named in the quote above, and both ends of that line are located. This is where planning documents put the substation, not a surveyed or built site, and a planned site can move.
How it was located: No point. TPIT places the station on the Ballinger to Red Creek 138 kV line; TPIT narrows it to the section between Ballinger and Weiss; Ballinger is in OpenStreetMap (AEP Ballinger Substation, way 119137383, 31.7412,-99.9446), Weiss is not; the line's far end is AEP San Angelo Red Creek (way 171818841, 31.5289,-100.3211). The station is somewhere on that line; no public document found that draws or describes its site.
Note: TPIT status Conceptual.
Sources: ERCOT TPIT, project(s) 99540 (release 39, 2026-10-01) · OpenStreetMap: Ballinger Substation (way 119137383), San Angelo Red Creek Substation (way 171818841) (OSM extract 2026-11-20). Map data © OpenStreetMap contributors, available under the Open Database License. Researched by Substation Scout; checked November 21, 2026.
Projects naming this substation
As the utility reported them in the current release. The tab is ERCOT’s; the status is the utility’s.
| Project | Utility | Status as reported | kV | Projected in service | Terminals | Substations named |
|---|---|---|---|---|---|---|
| Anastase: Construct New 138 kV Station Interconnect Rutile BESS to the new Anastase 138 kV station on the Ballinger to Red Creek 138 kV line between Ballinger and Weiss ERCOT project 99540 · utility no. TP2025343 |
AEP TNC Tier 4 |
Conceptual Future tab |
138 | Mar 2028 | Anastase Runnels County |
Anastase |
Changes between releases
Where two consecutive releases print different values for these projects (last ten releases).
| Release (data as of) | Project | What changed | Printed values |
|---|---|---|---|
| June 1, 2026 | 99540 | Moved between tabs | Current-year planned → Future |
| June 1, 2026 | 99540 | Projected in-service date | Jun 2026 → Mar 2028 |
| February 1, 2026 | 99540 | Moved between tabs | Future → Current-year planned |
| October 1, 2025 | 99540 | First listed | on the Future tab |
Source: ERCOT TPIT workbook, data as of October 1, 2026, retrieved 2026-10-26; posting page last checked 2026-11-23. Each row is cited by sheet and row number in the workbook.
Before relying on any of this
- TPIT lists substation work only where it changes a transmission line or autotransformer rating. A new load-serving substation that changes no rating may never appear in it.
- Every value is the Transmission Service Provider's own statement, compiled by ERCOT. Status and in-service dates are not ERCOT determinations.
- The workbook tab (Future, Current-year planned, Completed, Cancelled) is assigned by ERCOT from dates; the status column is the TSP's word. The two can disagree, and both are shown.
- In ERCOT's competitive areas the company named is the transmission and distribution wires company, not a retail electricity provider or a generator.
- ERCOT publishes the workbook about three times a year, plus occasional updates. A substation that is not listed may simply not be reported yet.
- Substation names are read from the workbook's "from" and "to" terminal columns; for rows with neither, from fixed patterns in the title and description. No language model reads this workbook.
- An entry is a name within a county, not a verified physical facility. A link to a HIFLD record means the names and counties agree exactly, not that the two are confirmed to be one facility.