Substation Scout

Nevill Road

Named in 1 listed project in ERCOT’s transmission project tracking workbook, in Pecos County. First named in the release with data as of June 1, 2026.

Pecoscounty as printed
345kV
LCRATSCutility
1projects listed

No HIFLD substation record has this name in this county.

Generation interconnection requests filed in Pecos, TX: ERCOT queue, 58 active of 63. Same county, not the same substation.

Projects naming this substation

As the utility reported them in the current release. The tab is ERCOT’s; the status is the utility’s.

ProjectUtilityStatus as reportedkVProjected in serviceTerminalsSubstations named
Nevill_Road_North_McCamey_Transmission_Line_Addition
Install a 345-kV circuit on the second position of the North McCamey – Nevill Road 345-kV transmission line from North McCamey Substation to a POI with Garland Power & Light (GP&L). Upgrade North McCamey Substation terminal equipment to interconnect the new transmission line.
ERCOT project 103248
LCRATSC
Tier 1
Planned
Future tab
345 Jun 2030 Nevill Road to North McCamey
Pecos / Upton County
Nevill Road, North McCamey

Changes between releases

Where two consecutive releases print different values for these projects (last ten releases).

Release (data as of)ProjectWhat changedPrinted values
July 13, 2026103248Projected in-service dateMay 2030 → Jun 2030
June 1, 2026103248First listedon the Future tab

Source: ERCOT TPIT workbook, data as of October 1, 2026, retrieved 2026-10-26; posting page last checked 2026-11-23. Each row is cited by sheet and row number in the workbook.