Sunstone

Named in 1 listed project in ERCOT’s transmission project tracking workbook, in Nueces County. First named in the release with data as of October 1, 2024.

Nuecescounty as printed
138kV
AEP TCC/ETTutility
1projects listed

Described as new. The quoted wording calls this substation new. “Sunstone: Construct New 138 kV Station” — project 87328 title, as the utility reported it

No HIFLD substation record has this name in this county.

Generation interconnection requests filed in Nueces, TX: ERCOT queue, 13 active of 13. Same county, not the same substation.

Location

Nueces County, TX

On a named line, no point. No point is published. The planning documents place it on the transmission line named in the quote above, and both ends of that line are located. This is where planning documents put the substation, not a surveyed or built site, and a planned site can move.

How it was located: No point. TPIT places the station on the Morris Street to Nueces Bay 138 kV line; both ends are in OpenStreetMap in Corpus Christi: AEP Morris Substation (way 371318815, 27.7844,-97.4056) and AEP Nueces Bay Substation (way 488507970, 27.8209,-97.4184), ~4 km apart. The station is somewhere on that line; no public document found that draws or describes its site.

Note: The City of Corpus Christi voted in September 2025 to cancel its Inner Harbor desalination contract with Kiewit and then sought a new design-build partner (secondary reporting), so the load this station serves has been in flux; TPIT still lists it as Planned (ISD 2027-10).

Sources: ERCOT TPIT, project(s) 87328 (release 39, 2026-10-01) · OpenStreetMap: Morris Substation (way 371318815), Nueces Bay Substation (way 488507970) (OSM extract 2026-11-20). Map data © OpenStreetMap contributors, available under the Open Database License. Researched by Substation Scout; checked November 21, 2026.

Projects naming this substation

As the utility reported them in the current release. The tab is ERCOT’s; the status is the utility’s.

ProjectUtilityStatus as reportedkVProjected in serviceTerminalsSubstations named
Sunstone: Construct New 138 kV Station
Interconnect the Inner Harbor Desalination Plant load to the new Sunstone 138 kV station on the Morris Street to Nueces Bay 138 kV line
ERCOT project 87328 · utility no. TP2022754
AEP TCC/ETT
Tier 4
Planned
Future tab
138 Oct 2027 Sunstone
Nueces County
Sunstone

Changes between releases

Where two consecutive releases print different values for these projects (last ten releases).

Release (data as of)ProjectWhat changedPrinted values
June 1, 202687328Projected in-service dateJun 2027 → Oct 2027
October 1, 202487328First listedon the Future tab

Source: ERCOT TPIT workbook, data as of October 1, 2026, retrieved 2026-10-26; posting page last checked 2026-11-23. Each row is cited by sheet and row number in the workbook.