Named in 1 listed project in ERCOT’s transmission project tracking workbook, in Nueces County. First named in the release with data as of June 1, 2024.

Nuecescounty as printed
138kV
AEP TCCutility
1projects listed

Described as new. The quoted wording calls this substation new. “new Seabird 138 kV station” — project 81783 description, as the utility reported it

No HIFLD substation record has this name in this county.

Generation interconnection requests filed in Nueces, TX: ERCOT queue, 13 active of 13. Same county, not the same substation.

Location

Nueces County, TX

On a named line, no point. No point is published. The planning documents place it on the transmission line named in the quote above, and both ends of that line are located. This is where planning documents put the substation, not a surveyed or built site, and a planned site can move.

How it was located: No point. TPIT places the station on the Homeport to Ingleside 138 kV line; both ends are in OpenStreetMap: AEP Homeport Substation (way 514740542, 27.8279,-97.2095) and AEP Ingleside Substation (way 514740548, 27.8721,-97.2168), ~5 km apart. The station is somewhere on that line; no public document found that draws or describes its site.

Note: County is unsettled: TPIT prints Nueces, but both ends of the Homeport - Ingleside line are at Ingleside on the San Patricio side of the county line (Nueces County reaches the area only across Corpus Christi Bay / Redfish Bay). TPIT status Conceptual.

Sources: ERCOT TPIT, project(s) 81783 (release 39, 2026-10-01) · OpenStreetMap: Homeport Substation (way 514740542), Ingleside Substation (way 514740548) (OSM extract 2026-11-20). Map data © OpenStreetMap contributors, available under the Open Database License. Researched by Substation Scout; checked November 21, 2026.

Projects naming this substation

As the utility reported them in the current release. The tab is ERCOT’s; the status is the utility’s.

ProjectUtilityStatus as reportedkVProjected in serviceTerminalsSubstations named
Ingleside to Seabird: Construct New 138 kV Line
Interconnect the Mu load to the new Seabird 138 kV station on the Homeport to Ingleside 138 kV line, construct a new 138 kV line from Ingleside to Seabird, and add capacitors
ERCOT project 81783
AEP TCC
Tier 4
Conceptual
Future tab
138 Dec 2028 Ingleside to Seabird
San Patricio / Nueces County
Ingleside, Seabird

Changes between releases

Where two consecutive releases print different values for these projects (last ten releases).

Release (data as of)ProjectWhat changedPrinted values
October 1, 202581783Projected in-service dateDec 2026 → Dec 2028
June 1, 202481783First listedon the Future tab

Source: ERCOT TPIT workbook, data as of October 1, 2026, retrieved 2026-10-26; posting page last checked 2026-11-23. Each row is cited by sheet and row number in the workbook.