Festin

Named in 1 listed project in ERCOT’s transmission project tracking workbook, in Nueces County. First named in the release with data as of February 1, 2025.

Nuecescounty as printed
345kV
AEP TCCutility
1projects listed

Described as new. The quoted wording calls this substation new. “Festin: Construct New 345 kV Station” — project 90025 title, as the utility reported it

No HIFLD substation record has this name in this county.

Generation interconnection requests filed in Nueces, TX: ERCOT queue, 13 active of 13. Same county, not the same substation.

Location

Nueces County, TX

On a named line, no point. No point is published. The planning documents place it on the transmission line named in the quote above, and both ends of that line are located. This is where planning documents put the substation, not a surveyed or built site, and a planned site can move.

How it was located: No point. TPIT places the station on the Lon Hill to Reforzar 345 kV line; Lon Hill is in OpenStreetMap (way 174682093, 27.8438,-97.6156) and Reforzar has a map-shown point on this tracker (Brooks County, ~27.25,-98.02); the existing line is OSM ways 174682105 and 174808891 (Lon Hill - North Edinburg, which Reforzar cuts). The station is somewhere on that line; no public document found that draws or describes its site.

Sources: ERCOT TPIT, project(s) 90025 (release 39, 2026-10-01) · OpenStreetMap: Lon Hill Substation; Lon Hill - North Edinburg 345 kV line (ways 174682105, 174808891) (OSM extract 2026-11-20). Map data © OpenStreetMap contributors, available under the Open Database License. Researched by Substation Scout; checked November 21, 2026.

Projects naming this substation

As the utility reported them in the current release. The tab is ERCOT’s; the status is the utility’s.

ProjectUtilityStatus as reportedkVProjected in serviceTerminalsSubstations named
Festin: Construct New 345 kV Station
Interconnect Sunscape Renewable Solar and Storage to the new Festin 345 kV station on the Lon Hill to Reforzar 345 kV line
ERCOT project 90025 · utility no. TP2024111
AEP TCC
Tier 4
Planned
Future tab
345 Jul 2028 Festin
Nueces County
Festin

Changes between releases

Where two consecutive releases print different values for these projects (last ten releases).

Release (data as of)ProjectWhat changedPrinted values
October 1, 202690025Projected in-service dateMay 2028 → Jul 2028
October 1, 202590025Projected in-service dateJul 2028 → May 2028
February 1, 202590025First listedon the Future tab

Source: ERCOT TPIT workbook, data as of October 1, 2026, retrieved 2026-10-26; posting page last checked 2026-11-23. Each row is cited by sheet and row number in the workbook.