Festin
Named in 1 listed project in ERCOT’s transmission project tracking workbook, in Nueces County. First named in the release with data as of February 1, 2025.
Described as new. The quoted wording calls this substation new. “Festin: Construct New 345 kV Station” — project 90025 title, as the utility reported it
No HIFLD substation record has this name in this county.
Generation interconnection requests filed in Nueces, TX: ERCOT queue, 13 active of 13. Same county, not the same substation.
Location
Nueces County, TX
On a named line, no point. No point is published. The planning documents place it on the transmission line named in the quote above, and both ends of that line are located. This is where planning documents put the substation, not a surveyed or built site, and a planned site can move.
How it was located: No point. TPIT places the station on the Lon Hill to Reforzar 345 kV line; Lon Hill is in OpenStreetMap (way 174682093, 27.8438,-97.6156) and Reforzar has a map-shown point on this tracker (Brooks County, ~27.25,-98.02); the existing line is OSM ways 174682105 and 174808891 (Lon Hill - North Edinburg, which Reforzar cuts). The station is somewhere on that line; no public document found that draws or describes its site.
Sources: ERCOT TPIT, project(s) 90025 (release 39, 2026-10-01) · OpenStreetMap: Lon Hill Substation; Lon Hill - North Edinburg 345 kV line (ways 174682105, 174808891) (OSM extract 2026-11-20). Map data © OpenStreetMap contributors, available under the Open Database License. Researched by Substation Scout; checked November 21, 2026.
Projects naming this substation
As the utility reported them in the current release. The tab is ERCOT’s; the status is the utility’s.
| Project | Utility | Status as reported | kV | Projected in service | Terminals | Substations named |
|---|---|---|---|---|---|---|
| Festin: Construct New 345 kV Station Interconnect Sunscape Renewable Solar and Storage to the new Festin 345 kV station on the Lon Hill to Reforzar 345 kV line ERCOT project 90025 · utility no. TP2024111 |
AEP TCC Tier 4 |
Planned Future tab |
345 | Jul 2028 | Festin Nueces County |
Festin |
Changes between releases
Where two consecutive releases print different values for these projects (last ten releases).
| Release (data as of) | Project | What changed | Printed values |
|---|---|---|---|
| October 1, 2026 | 90025 | Projected in-service date | May 2028 → Jul 2028 |
| October 1, 2025 | 90025 | Projected in-service date | Jul 2028 → May 2028 |
| February 1, 2025 | 90025 | First listed | on the Future tab |
Source: ERCOT TPIT workbook, data as of October 1, 2026, retrieved 2026-10-26; posting page last checked 2026-11-23. Each row is cited by sheet and row number in the workbook.
Before relying on any of this
- TPIT lists substation work only where it changes a transmission line or autotransformer rating. A new load-serving substation that changes no rating may never appear in it.
- Every value is the Transmission Service Provider's own statement, compiled by ERCOT. Status and in-service dates are not ERCOT determinations.
- The workbook tab (Future, Current-year planned, Completed, Cancelled) is assigned by ERCOT from dates; the status column is the TSP's word. The two can disagree, and both are shown.
- In ERCOT's competitive areas the company named is the transmission and distribution wires company, not a retail electricity provider or a generator.
- ERCOT publishes the workbook about three times a year, plus occasional updates. A substation that is not listed may simply not be reported yet.
- Substation names are read from the workbook's "from" and "to" terminal columns; for rows with neither, from fixed patterns in the title and description. No language model reads this workbook.
- An entry is a name within a county, not a verified physical facility. A link to a HIFLD record means the names and counties agree exactly, not that the two are confirmed to be one facility.