Substation Scout

Amber

Named in 0 listed projects in ERCOT’s transmission project tracking workbook, in Nueces County, plus 1 on its Cancelled tab. First named in the release with data as of June 1, 2024.

Nuecescounty as printed
345kV
AEP TCCutility
0projects listed

Projects cancelled. Every project naming Amber is on the Cancelled tab of ERCOT's workbook.

No HIFLD substation record has this name in this county.

Generation interconnection requests filed in Nueces, TX: ERCOT queue, 13 active of 13. Same county, not the same substation.

Projects naming this substation

As the utility reported them in the current release. The tab is ERCOT’s; the status is the utility’s.

No projects.

On the Cancelled tab

ProjectUtilityStatus as reportedkVProjected in serviceTerminalsSubstations named
Amber: Construct New 345 kV Station
Interconnect the Kappa load to the new Amber 345 kV station on the Blue Lacy to Reforzar and Blue Lacy to Nelson Sharpe 345 kV lines and add capacitors
ERCOT project 81697
AEP TCC
Tier 3
Conceptual
Cancelled tab
345 Dec 2026 Amber
Nueces County
Amber

Changes between releases

Where two consecutive releases print different values for these projects (last ten releases).

Release (data as of)ProjectWhat changedPrinted values
October 1, 202581697Moved between tabsFuture → Cancelled
June 1, 202481697First listedon the Future tab

Source: ERCOT TPIT workbook, data as of October 1, 2026, retrieved 2026-10-26; posting page last checked 2026-11-23. Each row is cited by sheet and row number in the workbook.