Ringgold Magnolia

Named in 1 listed project in ERCOT’s transmission project tracking workbook, in Montague County. First named in the release with data as of October 1, 2023.

Montaguecounty as printed
69kV
ONCORutility
1projects listed

No HIFLD substation record has this name in this county.

Generation interconnection requests filed in Montague, TX: ERCOT queue, 4 active of 6. Same county, not the same substation.

Projects naming this substation

As the utility reported them in the current release. The tab is ERCOT’s; the status is the utility’s.

ProjectUtilityStatus as reportedkVProjected in serviceTerminalsSubstations named
Rebuild Old Lake Sw - Ringgold Magnolia 69 kV line
ERCOT project 77174 · utility no. M3508
ONCOR
Tier 4
Planned
Completed tab
69 Dec 2025
actual 2025-12
Old Lake Switch to Ringgold Magnolia
Clay / Montague County
Old Lake Switch, Ringgold Magnolia

Changes between releases

Where two consecutive releases print different values for these projects (last ten releases).

Release (data as of)ProjectWhat changedPrinted values
October 1, 202677174Moved between tabsCurrent-year planned → Completed
October 1, 202577174Moved between tabsFuture → Current-year planned
October 1, 202577174Projected in-service dateMay 2026 → Dec 2025

Source: ERCOT TPIT workbook, data as of October 1, 2026, retrieved 2026-10-26; posting page last checked 2026-11-23. Each row is cited by sheet and row number in the workbook.