Cattleman
Named in 6 listed projects in ERCOT’s transmission project tracking workbook, in Mitchell County. First named in the release with data as of February 1, 2024.
Mitchellcounty as printed
138, 345kV
ONCORutility
6projects listed
No HIFLD substation record has this name in this county.
Generation interconnection requests filed in Mitchell, TX: ERCOT queue, 17 active of 19. Same county, not the same substation.
Projects naming this substation
As the utility reported them in the current release. The tab is ERCOT’s; the status is the utility’s.
| Project | Utility | Status as reported | kV | Projected in service | Terminals | Substations named |
|---|---|---|---|---|---|---|
| Longshore 345 kV Switch Rebuild Longshore 345 kV Switch Rebuild: Cattleman 345 kV Line Re-terminations ERCOT project 102846 · utility no. R8719 · RPG 23RPG034 |
ONCOR Tier 1 |
Planned Future tab |
345 | May 2027 | Cattleman to Longshore Mitchell / Howard County |
Cattleman, Longshore |
| Cattleman 345/138 kV Switch Construct a new 345/138 kV Switch to replace existing Morgan Creek Switch ERCOT project 72009 · utility no. R8647 · RPG 23RPG029 |
ONCOR Tier 1 |
In-Service Completed tab |
345 | Dec 2025 actual 2025-11 |
Cattleman to Cattleman Mitchell County |
Cattleman |
| Cattleman - Range Rider 138 kV Double-Circuit Line Construct a new 138 kV double-circuit line from Cattleman to Range Rider Switch ERCOT project 81225 · utility no. R8722 · RPG 23RPG029 |
ONCOR Tier 1 |
Planned Future tab |
138 | Dec 2027 | Cattleman to Range Rider Mitchell County |
Cattleman, Range Rider |
| Cattleman – Gascondades 345 kV Reroute Terminate Morgan Creek – Gascondades 345 kV Line into Cattleman 345 kV Switch ERCOT project 81227 · utility no. R8647 · RPG 23RPG029 |
ONCOR Tier 1 |
Planned Future tab |
345 | Jun 2027 | Cattleman to Gascondades Mitchell County |
Cattleman, Gascondades |
| Cattleman – Bitter Creek/Champion Creek 345 kV Reroute Terminate Morgan Creek – Bitter Creek/Champion Creek Double-Circuit 345 kV Line into Cattleman 345 kV Switch ERCOT project 81232 · utility no. R8647 · RPG 23RPG029 |
ONCOR Tier 1 |
Planned Future tab |
345 | Dec 2027 | Cattleman to Bitter Creek and Champion Creek Mitchell County |
Cattleman, Bitter Creek and Champion Creek |
| Ranger Camp – Cattleman 345 kV Double-Circuit Line Construct a new 345 kV double-circuit line from Ranger Camp to Cattleman ERCOT project 81274 · utility no. R8648 · RPG 23RPG029 |
ONCOR Tier 1 |
In-Service Completed tab |
345 | Mar 2026 actual 2026-06 |
Ranger Camp to Cattleman Mitchell County |
Ranger Camp, Cattleman |
Changes between releases
Where two consecutive releases print different values for these projects (last ten releases).
| Release (data as of) | Project | What changed | Printed values |
|---|---|---|---|
| October 1, 2026 | 81274 | Moved between tabs | Current-year planned → Completed |
| October 1, 2026 | 81274 | Status as reported | Planned → In-Service |
| June 1, 2026 | 102846 | Moved between tabs | Current-year planned → Future |
| June 1, 2026 | 102846 | Projected in-service date | Dec 2026 → May 2027 |
| June 1, 2026 | 81274 | Projected in-service date | Jan 2026 → Mar 2026 |
| February 1, 2026 | 102846 | First listed | on the Current-year planned tab |
| February 1, 2026 | 72009 | Moved between tabs | Current-year planned → Completed |
| February 1, 2026 | 72009 | Status as reported | Planned → In-Service |
| February 1, 2026 | 81225 | Projected in-service date | May 2027 → Dec 2027 |
| February 1, 2026 | 81227 | Projected in-service date | May 2027 → Jun 2027 |
| February 1, 2026 | 81232 | Projected in-service date | Dec 2026 → Dec 2027 |
| February 1, 2026 | 81274 | Projected in-service date | Dec 2025 → Jan 2026 |
| October 1, 2025 | 81225 | Projected in-service date | May 2028 → May 2027 |
| October 1, 2025 | 81227 | Projected in-service date | Jun 2027 → May 2027 |
| June 1, 2025 | 72009 | Moved between tabs | Future → Current-year planned |
| June 1, 2025 | 81227 | Projected in-service date | Dec 2026 → Jun 2027 |
| June 1, 2025 | 81232 | Projected in-service date | May 2027 → Dec 2026 |
| June 1, 2025 | 81274 | Moved between tabs | Future → Current-year planned |
| June 1, 2024 | 81225 | First listed | on the Future tab |
| June 1, 2024 | 81227 | First listed | on the Future tab |
| June 1, 2024 | 81232 | First listed | on the Future tab |
| June 1, 2024 | 81274 | First listed | on the Future tab |
Source: ERCOT TPIT workbook, data as of October 1, 2026, retrieved 2026-10-26; posting page last checked 2026-11-23. Each row is cited by sheet and row number in the workbook.
Before relying on any of this
- TPIT lists substation work only where it changes a transmission line or autotransformer rating. A new load-serving substation that changes no rating may never appear in it.
- Every value is the Transmission Service Provider's own statement, compiled by ERCOT. Status and in-service dates are not ERCOT determinations.
- The workbook tab (Future, Current-year planned, Completed, Cancelled) is assigned by ERCOT from dates; the status column is the TSP's word. The two can disagree, and both are shown.
- In ERCOT's competitive areas the company named is the transmission and distribution wires company, not a retail electricity provider or a generator.
- ERCOT publishes the workbook about three times a year, plus occasional updates. A substation that is not listed may simply not be reported yet.
- Substation names are read from the workbook's "from" and "to" terminal columns; for rows with neither, from fixed patterns in the title and description. No language model reads this workbook.
- An entry is a name within a county, not a verified physical facility. A link to a HIFLD record means the names and counties agree exactly, not that the two are confirmed to be one facility.