Marak
Named in 2 listed projects in ERCOT’s transmission project tracking workbook, in Milam County. First named in the release with data as of June 1, 2022.
Milamcounty as printed
69kV
ONCORutility
2projects listed
No HIFLD substation record has this name in this county.
Generation interconnection requests filed in Milam, TX: ERCOT queue, 30 active of 35. Same county, not the same substation.
Projects naming this substation
As the utility reported them in the current release. The tab is ERCOT’s; the status is the utility’s.
| Project | Utility | Status as reported | kV | Projected in service | Terminals | Substations named |
|---|---|---|---|---|---|---|
| Upgrade Temple - Minerva 69 kV Line Upgrade Temple - Marak 69 kV Line ERCOT project 66206A · utility no. R6186 · RPG 22RPG034 |
ONCOR Tier 3 |
Planned Current-year planned tab |
69 | Sep 2026 | Temple to Marak Bell / Milam County |
Temple, Marak |
| Upgrade Temple - Minerva 69 kV Line Upgrade Marak - Minerva 69 kV Line ERCOT project 66206B · utility no. R6186 · RPG 22RPG034 |
ONCOR Tier 3 |
Planned Future tab |
69 | Sep 2027 | Marak to Minerva Milam County |
Marak, Minerva |
Changes between releases
Where two consecutive releases print different values for these projects (last ten releases).
| Release (data as of) | Project | What changed | Printed values |
|---|---|---|---|
| February 1, 2026 | 66206A | First listed | on the Current-year planned tab |
| February 1, 2026 | 66206B | First listed | on the Future tab |
| June 1, 2025 | 66206A | No longer listed | future |
| June 1, 2025 | 66206B | No longer listed | future |
Source: ERCOT TPIT workbook, data as of October 1, 2026, retrieved 2026-10-26; posting page last checked 2026-11-23. Each row is cited by sheet and row number in the workbook.
Before relying on any of this
- TPIT lists substation work only where it changes a transmission line or autotransformer rating. A new load-serving substation that changes no rating may never appear in it.
- Every value is the Transmission Service Provider's own statement, compiled by ERCOT. Status and in-service dates are not ERCOT determinations.
- The workbook tab (Future, Current-year planned, Completed, Cancelled) is assigned by ERCOT from dates; the status column is the TSP's word. The two can disagree, and both are shown.
- In ERCOT's competitive areas the company named is the transmission and distribution wires company, not a retail electricity provider or a generator.
- ERCOT publishes the workbook about three times a year, plus occasional updates. A substation that is not listed may simply not be reported yet.
- Substation names are read from the workbook's "from" and "to" terminal columns; for rows with neither, from fixed patterns in the title and description. No language model reads this workbook.
- An entry is a name within a county, not a verified physical facility. A link to a HIFLD record means the names and counties agree exactly, not that the two are confirmed to be one facility.
Site Scanner