Midland East
Named in 3 listed projects in ERCOT’s transmission project tracking workbook, in Midland County. First named in the release with data as of February 1, 2015.
Also printed as: Midland East Switch
No HIFLD substation record has this name in this county.
Generation interconnection requests filed in Midland, TX: ERCOT queue, 7 active of 8 · SPP queue, 0 active of 1. Same county, not the same substation.
Projects naming this substation
As the utility reported them in the current release. The tab is ERCOT’s; the status is the utility’s.
| Project | Utility | Status as reported | kV | Projected in service | Terminals | Substations named |
|---|---|---|---|---|---|---|
| Sloan 138 kV Switch. Establish Sloan 138 kV Switch ERCOT project 80913 · utility no. R8659 |
ONCOR Tier 4 |
In-Service Completed tab |
138 | Dec 2025 actual 2025-05 |
Midessa South Switch to Odessa/Midland East Switch Midland County |
Midessa South Switch, Odessa, Midland East Switch |
| Midland East – Midland County NW 345 kV Line Rebuild Rebuild the existing 345 kV line and add a second circuit to the new line ERCOT project 81277 · utility no. R8729 · RPG 23RPG029 |
ONCOR Tier 1 |
Planned Future tab |
345 | Dec 2030 | Midland East to Midland County Northwest Midland County |
Midland East, Midland County Northwest |
| Rockhound - Midland East 345 kV Line Rebuild Rebuild the existing 345 kV line and add a second circuit to the new line ERCOT project 81302 · utility no. R3025 · RPG 23RPG029 |
ONCOR Tier 1 |
Planned Future tab |
345 | Dec 2029 | Rockhound to Midland East Midland County |
Rockhound, Midland East |
Changes between releases
Where two consecutive releases print different values for these projects (last ten releases).
| Release (data as of) | Project | What changed | Printed values |
|---|---|---|---|
| February 1, 2026 | 80913 | Moved between tabs | Current-year planned → Completed |
| February 1, 2026 | 80913 | Status as reported | Planned → In-Service |
| February 1, 2026 | 81302 | Projected in-service date | Sep 2029 → Dec 2029 |
| October 1, 2025 | 80913 | Moved between tabs | Completed → Current-year planned |
| October 1, 2025 | 80913 | Projected in-service date | May 2025 → Dec 2025 |
| October 1, 2025 | 81277 | Projected in-service date | May 2030 → Dec 2030 |
| October 1, 2025 | 81302 | Projected in-service date | Jun 2028 → Sep 2029 |
| June 1, 2025 | 80913 | Moved between tabs | Future → Completed |
| February 1, 2025 | 81277 | Projected in-service date | Dec 2028 → May 2030 |
| June 1, 2024 | 80913 | First listed | on the Future tab |
| June 1, 2024 | 81277 | First listed | on the Future tab |
| June 1, 2024 | 81302 | First listed | on the Future tab |
Source: ERCOT TPIT workbook, data as of October 1, 2026, retrieved 2026-10-26; posting page last checked 2026-11-23. Each row is cited by sheet and row number in the workbook.
Before relying on any of this
- TPIT lists substation work only where it changes a transmission line or autotransformer rating. A new load-serving substation that changes no rating may never appear in it.
- Every value is the Transmission Service Provider's own statement, compiled by ERCOT. Status and in-service dates are not ERCOT determinations.
- The workbook tab (Future, Current-year planned, Completed, Cancelled) is assigned by ERCOT from dates; the status column is the TSP's word. The two can disagree, and both are shown.
- In ERCOT's competitive areas the company named is the transmission and distribution wires company, not a retail electricity provider or a generator.
- ERCOT publishes the workbook about three times a year, plus occasional updates. A substation that is not listed may simply not be reported yet.
- Substation names are read from the workbook's "from" and "to" terminal columns; for rows with neither, from fixed patterns in the title and description. No language model reads this workbook.
- An entry is a name within a county, not a verified physical facility. A link to a HIFLD record means the names and counties agree exactly, not that the two are confirmed to be one facility.