Bader

Named in 1 listed project in ERCOT’s transmission project tracking workbook, in Medina County. First named in the release with data as of February 1, 2023.

Medinacounty as printed
138kV
STECutility
1projects listed

Expansion at an existing substation: new voltage level. The quoted wording describes a yard, bus or conversion at a voltage this substation is not otherwise shown at. The HIFLD record of the same name and county shows 69 kV. “Upgrade STEC Bader station to 138kV” — project 71917, as the utility reported it

A HIFLD substation record has the same name and county: BADER (MEDINA County). The names agree; that does not confirm they are the same facility.

Generation interconnection requests filed in Medina, TX: ERCOT queue, 7 active of 8. Same county, not the same substation.

Projects naming this substation

As the utility reported them in the current release. The tab is ERCOT’s; the status is the utility’s.

ProjectUtilityStatus as reportedkVProjected in serviceTerminalsSubstations named
Upgrade STEC castroville to Pearson to 138kV
Upgrade STEC Bader station to 138kV. Upgrade STEC Castroville to bader and bader to pearson to 138kV
ERCOT project 71917 · RPG 22RPG022
STEC
Tier 2
Under Construction
Current-year planned tab
138 Nov 2026 5808 to 5813
Medina County
Bader

Changes between releases

Where two consecutive releases print different values for these projects (last ten releases).

Release (data as of)ProjectWhat changedPrinted values
October 1, 202671917Status as reportedPlanned → Under Construction
October 1, 202671917Projected in-service dateJun 2026 → Nov 2026
February 1, 202671917Moved between tabsFuture → Current-year planned
February 1, 202671917Projected in-service dateApr 2026 → Jun 2026
February 1, 202571917Projected in-service dateMay 2025 → Apr 2026

Source: ERCOT TPIT workbook, data as of October 1, 2026, retrieved 2026-10-26; posting page last checked 2026-11-23. Each row is cited by sheet and row number in the workbook.