Named in 4 listed projects in ERCOT’s transmission project tracking workbook, in McLennan County. First named in the release with data as of June 1, 2025.

McLennancounty as printed
345kV
ONCORutility
4projects listed

No HIFLD substation record has this name in this county.

Generation interconnection requests filed in McLennan, TX: ERCOT queue, 18 active of 18. Same county, not the same substation.

Projects naming this substation

As the utility reported them in the current release. The tab is ERCOT’s; the status is the utility’s.

ProjectUtilityStatus as reportedkVProjected in serviceTerminalsSubstations named
Rebuild Possum Trot Switch - Belfalls-STR 26-4C 345 kV DCKT Line
ERCOT project 110154 · utility no. R6459 · RPG 25RPG043
ONCOR
Tier 1
Planned
Future tab
345 May 2030 Possum Trot to Belfalls
McLennan / Bell County
Possum Trot, Belfalls
Rebuild Possum Trot - St Johns Switch - Bale Switch - Stranger Switch 345 kV Line
ERCOT project 110160 · utility no. R6429 · RPG 25RPG043
ONCOR
Tier 1
Planned
Future tab
345 May 2031 Possum Trot to Stranger
McLennan / Limestone County
Possum Trot, Stranger
Rebuild Possum Trot - Lake Hall Switch - Tradinghouse Switch 345 kV Line
ERCOT project 110170 · utility no. R1717 · RPG 25RPG043
ONCOR
Tier 1
Planned
Future tab
345 May 2031 Possum Trot to Tradinghouse
McLennan County
Possum Trot, Tradinghouse
Lake Creek - Rattlesnake Road 345 kV Line
Establish Possum Trot 345 kV Switch
ERCOT project 78361B · utility no. R6276 · RPG 23RPG022
ONCOR
Tier 3
Planned
Current-year planned tab
345 Dec 2026 Possum Trot to Possum Trot
McLennan County
Possum Trot

Changes between releases

Where two consecutive releases print different values for these projects (last ten releases).

Release (data as of)ProjectWhat changedPrinted values
July 13, 2026110154First listedon the Future tab
July 13, 2026110160First listedon the Future tab
July 13, 2026110170First listedon the Future tab
June 1, 202678361BProjected in-service dateMay 2026 → Dec 2026
February 1, 202678361BMoved between tabsFuture → Current-year planned
June 1, 202578361BFirst listedon the Future tab

Source: ERCOT TPIT workbook, data as of October 1, 2026, retrieved 2026-10-26; posting page last checked 2026-11-23. Each row is cited by sheet and row number in the workbook.

Before relying on any of this

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first