Lake Creek
Named in 2 listed projects in ERCOT’s transmission project tracking workbook, in McLennan County. First named in the release with data as of February 1, 2015.
Also printed as: Lake Creek Switch
A HIFLD substation record has the same name and county: LAKE CREEK (MCLENNAN County). The names agree; that does not confirm they are the same facility.
Generation interconnection requests filed in McLennan, TX: ERCOT queue, 18 active of 18. Same county, not the same substation.
Projects naming this substation
As the utility reported them in the current release. The tab is ERCOT’s; the status is the utility’s.
| Project | Utility | Status as reported | kV | Projected in service | Terminals | Substations named |
|---|---|---|---|---|---|---|
| Rebuild the Lake Creek Switch - Riesel Switch 138 kV Line ERCOT project 110006 · utility no. R6433 |
ONCOR Tier 4 |
Conceptual Future tab |
138 | May 2030 | Lake Creek Switch to Riesel Switch McLennan / Falls County |
Lake Creek Switch, Riesel Switch |
| Lake Creek - Rattlesnake Road 345 kV Line Establish Lake Creek Switch - St Johns 345 kV Line, rebuild the Lake Creek Switch - Rattlesnake Road 345 kV Line, and install second circuit from Lake Creek Switch - Rattlesnake Road Switch ERCOT project 78361A · utility no. R6276 · RPG 23RPG022 |
ONCOR Tier 3 |
Planned Current-year planned tab |
345 | Dec 2026 | Lake Creek to Rattlesnake Road McLennan County |
Lake Creek, Rattlesnake Road |
Changes between releases
Where two consecutive releases print different values for these projects (last ten releases).
| Release (data as of) | Project | What changed | Printed values |
|---|---|---|---|
| July 13, 2026 | 110006 | First listed | on the Future tab |
| June 1, 2026 | 78361A | Projected in-service date | May 2026 → Dec 2026 |
| February 1, 2026 | 78361A | Moved between tabs | Future → Current-year planned |
| June 1, 2025 | 78361A | First listed | on the Future tab |
Source: ERCOT TPIT workbook, data as of October 1, 2026, retrieved 2026-10-26; posting page last checked 2026-11-23. Each row is cited by sheet and row number in the workbook.
Before relying on any of this
- TPIT lists substation work only where it changes a transmission line or autotransformer rating. A new load-serving substation that changes no rating may never appear in it.
- Every value is the Transmission Service Provider's own statement, compiled by ERCOT. Status and in-service dates are not ERCOT determinations.
- The workbook tab (Future, Current-year planned, Completed, Cancelled) is assigned by ERCOT from dates; the status column is the TSP's word. The two can disagree, and both are shown.
- In ERCOT's competitive areas the company named is the transmission and distribution wires company, not a retail electricity provider or a generator.
- ERCOT publishes the workbook about three times a year, plus occasional updates. A substation that is not listed may simply not be reported yet.
- Substation names are read from the workbook's "from" and "to" terminal columns; for rows with neither, from fixed patterns in the title and description. No language model reads this workbook.
- An entry is a name within a county, not a verified physical facility. A link to a HIFLD record means the names and counties agree exactly, not that the two are confirmed to be one facility.