Named in 1 listed project in ERCOT’s transmission project tracking workbook, in Maverick County. First named in the release with data as of February 1, 2024.

Maverickcounty as printed
138kV
LCRATSCutility
1projects listed

Described as new. The quoted wording calls this substation new. “new 138-kV Sunglow Substation” — project 73895 description, as the utility reported it

Reported complete. Project 73895 is on the Completed tab (actual in-service 2025-03), as the utility reported it. That indicates the substation may now be built; it is not a confirmation.

No HIFLD substation record has this name in this county.

Generation interconnection requests filed in Maverick, TX: ERCOT queue, 8 active of 8. Same county, not the same substation.

Location

Maverick County, TX

County only. A source prints the county; no point is published. This is where planning documents put the substation, not a surveyed or built site, and a planned site can move.

How it was located: No point. TPIT says only that the station sits between LCRA TSC T627 and Rio Grande Electric Cooperative's Rosita Creek Substation (OSM way 20841019, 28.6992,-100.4051); it does not name T627's other end, so the line cannot be bounded. No utility page, PUCT filing or OSM feature named Sunglow was found.

Note: TPIT 73895 is on the Completed tab with ISD 2025-03 (status still 'Planned'), so the station may already be in service. TPIT calls Rosita Creek an LCRA substation; OSM tags it Rio Grande Electric Cooperative.

Sources: ERCOT TPIT, project(s) 73895 (release 39, 2026-10-01) · OpenStreetMap: Rosita Creek Substation (way 20841019) (OSM extract 2026-11-20). Map data © OpenStreetMap contributors, available under the Open Database License. Researched by Substation Scout; checked November 21, 2026.

Projects naming this substation

As the utility reported them in the current release. The tab is ERCOT’s; the status is the utility’s.

ProjectUtilityStatus as reportedkVProjected in serviceTerminalsSubstations named
Sunglow Substation Addition
This project provides a point of interconnection for a new battery energy storage resource at a new 138-kV Sunglow Substation between LCRA TSC T627 and LCRA Rosita Creek Substation.
ERCOT project 73895
LCRATSC
Tier 4
Planned
Completed tab
138 Mar 2025
actual 2025-03
Sunglow
Maverick County
Sunglow

Changes between releases

Where two consecutive releases print different values for these projects (last ten releases).

Release (data as of)ProjectWhat changedPrinted values
June 1, 202573895Moved between tabsFuture → Completed
February 1, 202573895Projected in-service dateJan 2025 → Mar 2025
October 1, 202473895Projected in-service dateOct 2026 → Jan 2025

Source: ERCOT TPIT workbook, data as of October 1, 2026, retrieved 2026-10-26; posting page last checked 2026-11-23. Each row is cited by sheet and row number in the workbook.