Substation Scout

Midland East

Named in 1 listed project in ERCOT’s transmission project tracking workbook, in Martin County. First named in the release with data as of February 1, 2015.

Martincounty as printed
345kV
ONCORutility
1projects listed

No HIFLD substation record has this name in this county.

Generation interconnection requests filed in Martin, TX: ERCOT queue, 3 active of 4. Same county, not the same substation.

Projects naming this substation

As the utility reported them in the current release. The tab is ERCOT’s; the status is the utility’s.

ProjectUtilityStatus as reportedkVProjected in serviceTerminalsSubstations named
Rockhound 345/138 kV Switch
Construct a new 345/138 kV Switch
ERCOT project 78374 · utility no. R8705 · RPG 24RPG002
ONCOR
Tier 3
Under Construction
Completed tab
345 Mar 2025
actual 2025-02
Falcon Seaboard to Midland East
Midland / Martin County
Falcon Seaboard, Midland East

Changes between releases

Where two consecutive releases print different values for these projects (last ten releases).

Release (data as of)ProjectWhat changedPrinted values
June 1, 202578374Moved between tabsFuture → Completed
February 1, 202578374Status as reportedPlanned → Under Construction
February 1, 202578374Projected in-service dateDec 2024 → Mar 2025

Source: ERCOT TPIT workbook, data as of October 1, 2026, retrieved 2026-10-26; posting page last checked 2026-11-23. Each row is cited by sheet and row number in the workbook.