Substation Scout

San Miguel

Named in 1 listed project in ERCOT’s transmission project tracking workbook, in Live Oak County. First named in the release with data as of July 13, 2026.

Live Oakcounty as printed
138kV
STECutility
1projects listed

No HIFLD substation record has this name in this county (a record of the same name exists in another county).

Generation interconnection requests filed in Live Oak, TX: ERCOT queue, 5 active of 8. Same county, not the same substation.

Projects naming this substation

As the utility reported them in the current release. The tab is ERCOT’s; the status is the utility’s.

ProjectUtilityStatus as reportedkVProjected in serviceTerminalsSubstations named
STEC Hammer Load Project Phase 2
-Tap STEC San Miguel to Cruce 345kV ckt 1 to create a new 345kV station -Install 2 345/138kV autos and expand the new station to a 345/138 station - Construct and approximately 18.25 mile 138kV transmission line from the new 138kV station to STEC George West
ERCOT project 110453
STEC
Tier 3
Conceptual
Future tab
138 Jun 2028 George West, San Miguel to Cruce
Live Oak County
George West, San Miguel, Cruce

Changes between releases

Where two consecutive releases print different values for these projects (last ten releases).

Release (data as of)ProjectWhat changedPrinted values
July 13, 2026110453First listedon the Future tab

Source: ERCOT TPIT workbook, data as of October 1, 2026, retrieved 2026-10-26; posting page last checked 2026-11-23. Each row is cited by sheet and row number in the workbook.

Before relying on any of this

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first