Substation Scout

Able Springs

Named in 1 listed project in ERCOT’s transmission project tracking workbook, in Kaufman County. First named in the release with data as of June 1, 2022.

Kaufmancounty as printed
69kV
ONCORutility
1projects listed

No HIFLD substation record has this name in this county.

Generation interconnection requests filed in Kaufman, TX: ERCOT queue, 16 active of 18. Same county, not the same substation.

Projects naming this substation

As the utility reported them in the current release. The tab is ERCOT’s; the status is the utility’s.

ProjectUtilityStatus as reportedkVProjected in serviceTerminalsSubstations named
Edgewood Switch – Royse Switch 138 kV Line
Rebuild and convert the Edgewood-Iron Bridge 69 kV to 138 kV operation
ERCOT project 68706 · utility no. M3227
ONCOR
Tier 4
Planned
Future tab
69 Dec 2027 Edgewood to Able Springs
Van Zandt / Kaufman County
Edgewood, Able Springs

Changes between releases

Where two consecutive releases print different values for these projects (last ten releases).

Release (data as of)ProjectWhat changedPrinted values
October 1, 202568706Projected in-service dateDec 2026 → Dec 2027

Source: ERCOT TPIT workbook, data as of October 1, 2026, retrieved 2026-10-26; posting page last checked 2026-11-23. Each row is cited by sheet and row number in the workbook.

Before relying on any of this

Site Scanner

Before you spend weeks on a site, spend seconds screening it.

Scan a site →

Or read a sample report first