Substation Scout

Cascabel

Named in 2 listed projects in ERCOT’s transmission project tracking workbook, in Jones County. First named in the release with data as of June 1, 2025.

Jonescounty as printed
345kV
AEP TNC/ETT, ETTutility
2projects listed

Described as new. The quoted wording calls this substation new. “Cascabel: Construct New 345 kV Station” — project 90059 title, as the utility reported it

No HIFLD substation record has this name in this county.

Generation interconnection requests filed in Jones, TX: ERCOT queue, 18 active of 21. Same county, not the same substation.

Location

Jones County, TX

County only. A source prints the county; no point is published. This is where planning documents put the substation, not a surveyed or built site, and a planned site can move.

Note: TSP differs between projects: ETT (90059) and AEP TNC/ETT (110417).

Sources: ERCOT TPIT, projects 110417, 90059 (release 39, 2026-10-01), sheet FutureTPIT100126NoCost. Researched by Substation Scout; checked November 21, 2026.

Projects naming this substation

As the utility reported them in the current release. The tab is ERCOT’s; the status is the utility’s.

ProjectUtilityStatus as reportedkVProjected in serviceTerminalsSubstations named
Cascabel: Install New 345 kV Capacitor Bank
Install a new capacitor bank at the Cascabel 345 kV station
ERCOT project 110417
AEP TNC/ETT
Tier 4
Conceptual
Future tab
345 Nov 2028 Cascabel
Jones County
Cascabel
Cascabel: Construct New 345 kV Station
Interconnect Moccasin Solar to the new Cascabel 345 kV station on the Clear Crossing to Figaro 345 kV line between Clear Crossing and Kirchoff
ERCOT project 90059 · utility no. TP2024121
ETT
Tier 4
Planned
Future tab
345 Jan 2027 Cascabel
Jones County
Cascabel

Changes between releases

Where two consecutive releases print different values for these projects (last ten releases).

Release (data as of)ProjectWhat changedPrinted values
October 1, 202690059Moved between tabsCurrent-year planned → Future
October 1, 202690059Projected in-service dateDec 2026 → Jan 2027
July 13, 2026110417First listedon the Future tab
June 1, 202690059Moved between tabsFuture → Current-year planned
June 1, 202690059Projected in-service dateMar 2027 → Dec 2026
February 1, 202690059Projected in-service dateNov 2026 → Mar 2027
June 1, 202590059First listedon the Future tab

Source: ERCOT TPIT workbook, data as of October 1, 2026, retrieved 2026-10-26; posting page last checked 2026-11-23. Each row is cited by sheet and row number in the workbook.